Follow us!

    Re: machenics lein / texas Roo

    Posted by Curmudgeon---Don't Open My Last Post on 3/15/05

    I don't know what happened. Tried to copy a single section, but the
    whole damn chapter appeared.

    On 3/15/05, Curmudgeon wrote:
    > TEXAS PROPERTY CODE
    > [Mechanic's Lien Statutes in effect as of August 1, 2003]
    > [Does not include any changes which may become effective at a later
    > date]
    >
    > CHAPTER 53. MECHANIC'S, CONTRACTOR'S, OR MATERIALMAN'S LIEN
    >
    > TABLE OF CONTENTS
    >
    > SUBCHAPTER A. GENERAL PROVISIONS
    >
    >
    > § 53.001. Definitions
    >
    > § 53.002. More Than One Original Contractor
    >
    > § 53.003. Notices"
    >
    > § 53.004. reserved for expansion
    >
    > § 53.020. reserved for expansion
    > SUBCHAPTER B PERSONS ENTITLED TO LIEN; SUBJECT PROPERTY
    >
    >
    > § 53.021. Persons Entitled to Lien
    >
    > § 53.022. Property to Which Lien Extends
    >
    > § 53.023. Payment Secured by Lien
    >
    > § 53.024. Limitation on Subcontractor's Lien
    >
    > § 53.025. Limitation on Ordinary Retainage Lien
    >
    > § 53.026. Sham Contract
    >
    > § 53.027. reserved for expansion
    >
    > § 53.028. reserved for expansion
    > SUBCHAPTER C PROCEDURE FOR PERFECTING LIEN
    >
    >
    > § 53.051. Necessary Procedures
    >
    > § 53.052. Filing of Affidavit
    >
    > § 53.053. Accrual of Indebtedness
    >
    > § 53.054. Contents of Affidavit
    >
    > § 53.055. Notice of Filed Affidavit
    >
    > § 53.056. Derivative Claimant: Notice to Owner or Original
    > Contractor
    >
    > § 53.057. Derivative Claimant: Notice for Contractual Retainage
    > Claim
    >
    > § 53.058. Derivative Claimant: Notice for Specially Fabricated Items
    >
    > § 53.059. Repealed by Acts 1997, 75th Leg., ch. 526, s 24, eff.
    > Sept. 1, 1997
    >
    > § 53.060. reserved for expansion
    >
    > § 53.080. reserved for expansion
    > SUBCHAPTER D FUNDS WITHHELD BY OWNER FOLLOWING NOTICE
    >
    >
    > § 53.081. Authority to Withhold Funds for Benefit of Claimants
    >
    > § 53.082. Time for Which Funds are Withheld
    >
    > § 53.083. Payment to Claimant on Demand
    >
    > § 53.084. Owner's Liability
    >
    > § 53.085. Affidavit Required
    >
    > § 53.086. reserved for expansion
    >
    > § 53.100. reserved for expansion
    > SUBCHAPTER E REQUIRED RETAINAGE FOR BENEFIT OF LIEN CLAIMANTS
    >
    >
    > § 53.101. Required Retainage
    >
    > § 53.102. Payment Secured by Retainage
    >
    > § 53.103. Lien on Retained Funds
    >
    > § 53.104. Preferences
    >
    > § 53.105. Owner's Liability for Failure to Retain
    >
    > § 53.106. Affidavit of Completion
    >
    > § 53.107. reserved for expansion
    >
    > § 53.120. reserved for expansion
    > SUBCHAPTER F PRIORITIES AND PREFERENCES
    >
    >
    > § 53.121. Preference Over Other Creditors
    >
    > § 53.122. Equality of Mechanic's Liens
    >
    > § 53.123. Priority of Mechanic's Lien Over Other Liens
    >
    > § 53.124. Inception of Mechanic's Lien
    >
    > § 53.125. reserved for expansion
    >
    > § 53.150. reserved for expansion
    > SUBCHAPTER G RELEASE AND FORECLOSURE; ACTION ON CLAIM
    >
    >
    > § 53.151. Enforcement of Remedies Against Money Due Original
    > Contractor
    >
    > or Subcontractor
    >
    > § 53.152. Release of Claim or Lien
    >
    > § 53.153. Defense of Actions
    >
    > § 53.154. Foreclosure
    >
    > § 53.155. Transfer of Property Sold
    >
    > § 53.156. Costs and Attorney's Fees
    >
    > § 53.157. Discharge of Lien
    >
    > § 53.158. Period for Bringing Suit to Foreclose Lien
    >
    > § 53.159. Obligation to Furnish Information
    >
    > § 53.160. Summary Motion to Remove Invalid or Unenforceable Lien
    >
    > § 53.161. Bond Requirements After Order to Remove
    >
    > § 53.162. Revival of Removed Lien
    >
    > § 53.163. reserved for expansion
    >
    > § 53.170. reserved for expansion
    > SUBCHAPTER H BOND TO INDEMNIFY AGAINST LIEN
    >
    >
    > § 53.171. Bond
    >
    > § 53.172. Bond Requirements
    >
    > § 53.173. Notice of Bond
    >
    > § 53.174. Recording of Bond and Notice
    >
    > § 53.175. Action on Bond
    >
    > § 53.176. Repealed by Acts 1989, 71st Leg., ch. 1138, s 39(2), eff.
    > Sept. 1, 1989
    >
    > § 53.177. reserved for expansion
    >
    > § 53.200. reserved for expansion
    > SUBCHAPTER I BOND TO PAY LIENS OR CLAIMS
    >
    >
    > § 53.201. Bond
    >
    > § 53.202. Bond Requirements
    >
    > § 53.203. Recording of Bond and Contract
    >
    > § 53.204. Reliance on Record
    >
    > § 53.205. Enforceable Claims
    >
    > § 53.206. Perfection of Claim
    >
    > § 53.207. Owner's Notice of Claim to Surety
    >
    > § 53.208. Action on Bond
    >
    > § 53.209. Repealed by Acts 1989, 71st Leg., ch. 1138, s 39(3), eff.
    > Sept. 1, 1989
    >
    > § 53.210. Claims in Excess of Bond Amount
    >
    > § 53.211. Attempted Compliance
    >
    > § 53.212. reserved for expansion
    >
    > § 53.230. reserved for expansion
    > SUBCHAPTER J LIEN ON MONEY DUE PUBLIC WORKS CONTRACTOR
    >
    >
    > § 53.231. Lien
    >
    > § 53.232. To Whom Notice Given; Manner
    >
    > § 53.233. Contents of Notice
    >
    > § 53.234. Time for Notice
    >
    > § 53.235. Official to Retain Funds
    >
    > § 53.236. Bond for Release of Lien
    >
    > § 53.237. Bond Requirements
    >
    > § 53.238. Notice of Bond
    >
    > § 53.239. Action on Bond
    >
    > § 53.240. Repealed by Acts 1989, 71st Leg., ch. 1138, s 39(4), eff.
    > Sept. 1, 1989
    > SUBCHAPTER K RESIDENTIAL CONSTRUCTION PROJECTS
    >
    >
    > § 53.251. Procedures for Residential Construction Projects
    >
    > § 53.252. Derivative Claimant: Notice to Owner or Original
    > Contractor
    >
    > § 53.253. Derivative Claimant: Notice for Specially Fabricated Items
    >
    > § 53.254. Homestead
    >
    > § 53.255. Disclosure Statement Required for Residential Construction
    > Contract
    >
    > § 53.256. List of Subcontractors and Suppliers
    >
    > § 53.257. Provisions Related to Closing of Loan for Construction of
    > Improvements
    >
    > § 53.258. Disbursements of Funds
    >
    > § 53.259. Final Bills-Paid Affidavit Required
    >
    > § 53.260. Conveyance to Contractor Not Required
    >
    > CHAPTER 53. MECHANIC'S, CONTRACTOR'S, OR MATERIALMAN'S LIEN
    >
    >
    > SUBCHAPTER A. GENERAL PROVISIONS
    >
    > § 53.001. Definitions
    >
    > In this chapter:
    >
    >
    > (1) "Contract price" means the cost to the owner for any part of
    > construction or repair performed under an original contract.
    >
    > (2) "Improvement" includes:
    >
    > (A) abutting sidewalks and streets and utilities in or on those
    > sidewalks and streets;
    >
    > (B) clearing, grubbing, draining, or fencing of land;
    >
    > (C) wells, cisterns, tanks, reservoirs, or artificial lakes or pools
    > made for supplying or storing water;
    >
    > (D) pumps, siphons, and windmills or other machinery or apparatuses
    > used for raising water for stock, domestic use, or irrigation; and
    >
    > (E) planting orchard trees, grubbing out orchards and replacing
    > trees, and pruning of orchard trees.
    >
    > (3) "Labor" means labor used in the direct prosecution of the work.
    >
    > (4) "Material" means all or part of:
    >
    > (A) the material, machinery, fixtures, or tools incorporated into
    > the work, consumed in the direct prosecution of the work, or ordered
    > and delivered for incorporation or consumption;
    >
    > (B) rent at a reasonable rate and actual running repairs at a
    > reasonable cost for construction equipment used or reasonably
    > required and delivered for use in the direct prosecution of the work
    > at the site of the construction or repair; or
    >
    > (C) power, water, fuel, and lubricants consumed or ordered and
    > delivered for consumption in the direct prosecution of the work.
    >
    > (5) "Mechanic's lien" means the lien provided by this chapter.
    >
    > (6) "Original contract" means an agreement to which an owner is a
    > party either directly or by implication of law.
    >
    > (7) "Original contractor" means a person contracting with an owner
    > either directly or through the owner's agent.
    >
    > (8) "Residence" means a single-family house, duplex, triplex, or
    > quadruplex or a unit in a multiunit structure used for residential
    > purposes that is:
    >
    > (A) owned by one or more adult persons; and (B) used or intended to
    > be used as a dwelling by one of the owners.
    >
    > (9) "Residential construction contract" means a contract between an
    > owner and a contractor in which the contractor agrees to construct
    > or repair the owner's residence, including improvements appurtenant
    > to the residence.
    >
    > (10) "Residential construction project" means a project for the
    > construction or repair of a new or existing residence, including
    > improvements appurtenant to the residence, as provided by a
    > residential construction contract.
    >
    > (11) "Retainage" means an amount representing part of a contract
    > payment that is not required to be paid to the claimant within the
    > month following the month in which labor is performed, material is
    > furnished, or specially fabricated material is delivered. The term
    > does not include retainage under Subchapter E. [FN1]
    >
    > (12) "Specially fabricated material" means material fabricated for
    > use as a component of the construction or repair so as to be
    > reasonably unsuitable for use elsewhere.
    >
    > (13) "Subcontractor" means a person who has furnished labor or
    > materials to fulfill an obligation to an original contractor or to a
    > subcontractor to perform all or part of the work required by an
    > original contract.
    >
    > (14) "Work" means any part of construction or repair performed under
    > an original contract.
    >
    > (15) "Completion" of an original contract means the actual
    > completion of the work, including any extras or change orders
    > reasonably required or contemplated under the original contract,
    > other than warranty work or replacement or repair of the work
    > performed under the contract.
    > § 53.002. More Than One Original Contractor
    >
    > On any work there may be more than one original contractor for
    > purposes of this chapter.
    >
    > § 53.003. Notices
    >
    >
    > (a) This section applies to notices required by Subchapters B
    > through G and K. [FN1]
    >
    > (b) Any notice or other written communication may be delivered in
    > person to the party entitled to the notice or to that party's agent,
    > regardless of the manner prescribed by law.
    >
    > (c) If notice is sent by registered or certified mail, deposit or
    > mailing of the notice in the United States mail in the form required
    > constitutes compliance with the notice requirement. This subsection
    > does not apply if the law requires receipt of the notice by the
    > person to whom it is directed.
    >
    > (d) If a written notice is received by the person entitled to
    > receive it, the method by which the notice was delivered is
    > immaterial.
    > [Sections 53.004 to 53.020 reserved for expansion]
    >
    > SUBCHAPTER B PERSONS ENTITLED TO LIEN; SUBJECT PROPERTY
    >
    > § 53.021. Persons Entitled to Lien
    >
    >
    > (a) A person has a lien if:
    >
    > (1) the person labors, specially fabricates material, or furnishes
    > labor or materials for construction or repair in this state of:
    >
    > (A) a house, building, or improvement;
    >
    > (B) a levee or embankment to be erected for the reclamation of
    > overflow land along a river or creek; or
    >
    > (C) a railroad; and
    >
    > (2) the person labors, specially fabricates the material, or
    > furnishes the labor or materials under or by virtue of a contract
    > with the owner or the owner's agent, trustee, receiver, contractor,
    > or subcontractor.
    >
    > (b) A person who specially fabricates material has a lien even if
    > the material is not delivered.
    >
    > (c) An architect, engineer, or surveyor who prepares a plan or plat
    > under or by virtue of a written contract with the owner or the
    > owner's agent, trustee, or receiver in connection with the actual or
    > proposed design, construction, or repair of improvements on real
    > property or the location of the boundaries of real property has a
    > lien on the property.
    >
    > (d) A person who provides labor, plant material, or other supplies
    > for the installation of landscaping for a house, building, or
    > improvement, including the construction of a retention pond,
    > retaining wall, berm, irrigation system, fountain, or other similar
    > installation, under or by virtue of a written contract with the
    > owner or the owner's agent, trustee, or receiver has a lien on the
    > property.
    > § 53.022. Property to Which Lien Extends
    >
    >
    > (a) The lien extends to the house, building, fixtures, or
    > improvements, the land reclaimed from overflow, or the railroad and
    > all of its properties, and to each lot of land necessarily connected
    > or reclaimed.
    >
    > (b) The lien does not extend to abutting sidewalks, streets, and
    > utilities that are public property.
    >
    > (c) A lien against land in a city, town, or village extends to each
    > lot on which the house, building, or improvement is situated or on
    > which the labor was performed.
    >
    > (d) A lien against land not in a city, town, or village extends to
    > not more than 50 acres on which the house, building, or improvement
    > is situated or on which the labor was performed.
    > § 53.023. Payment Secured by Lien
    >
    >
    > The lien secures payment for:
    >
    > (1) the labor done or material furnished for the construction or
    > repair;
    >
    > (2) the specially fabricated material, even if the material has not
    > been delivered or incorporated into the construction or repair, less
    > its fair salvage value; or
    >
    > (3) the preparation of a plan or plat by an architect, engineer, or
    > surveyor in accordance with Section 53.021(c).
    > § 53.024. Limitation on Subcontractor's Lien
    >
    >
    > The amount of a lien claimed by a subcontractor may not exceed:
    >
    > (1) an amount equal to the proportion of the total subcontract price
    > that the sum of the labor performed, materials furnished, materials
    > specially fabricated, reasonable overhead costs incurred, and
    > proportionate profit margin bears to the total subcontract price;
    > minus
    >
    > (2) the sum of previous payments received by the claimant on the
    > subcontract.
    > § 53.025. Limitation on Ordinary Retainage Lien
    >
    >
    > A lien for retainage is valid only for the amount specified to be
    > retained in the contract, including any amendments to the contract,
    > between the claimant and the original contractor or between the
    > claimant and a subcontractor.
    > § 53.026. Sham Contract
    >
    >
    > (a) A person who labors, specially fabricates materials, or
    > furnishes labor or materials under a direct contractual relationship
    > with another person is considered to be in direct contractual
    > relationship with the owner and has a lien as an original
    > contractor, if:
    >
    > (1) the owner contracted with the other person for the construction
    > or repair of a house, building, or improvements and the owner can
    > effectively control that person through ownership of voting stock,
    > interlocking directorships, or otherwise;
    >
    > (2) the owner contracted with the other person for the construction
    > or repair of a house, building, or improvements and that other
    > person can effectively control the owner through ownership of voting
    > stock, interlocking directorships, or otherwise; or
    >
    > (3) the owner contracted with the other person for the construction
    > or repair of a house, building, or improvements and the contract was
    > made without good faith intention of the parties that the other
    > person was to perform the contract.
    >
    > (b) In this section, "owner" does not include a person who has or
    > claims a security interest only.
    > [Sections 53.027 to 53.050 reserved for expansion]
    >
    >
    > SUBCHAPTER C PROCEDURE FOR PERFECTING LIEN
    >
    > § 53.051. Necessary Procedures
    >
    >
    > To perfect the lien, a person must comply with this subchapter.
    > § 53.052. Filing of Affidavit
    >
    >
    > (a) Except as provided by Subsection (b), the person claiming the
    > lien must file an affidavit with the county clerk of the county in
    > which the property is located or into which the railroad extends not
    > later than the 15th day of the fourth calendar month after the day
    > on which the indebtedness accrues.
    >
    > (b) A person claiming a lien arising from a residential construction
    > project must file an affidavit with the county clerk of the county
    > in which the property is located not later than the 15th day of the
    > third calendar month after the day on which the indebtedness
    > accrues.
    >
    > (c) The county clerk shall record the affidavit in records kept for
    > that purpose and shall index and cross-index the affidavit in the
    > names of the claimant, the original contractor, and the owner.
    > Failure of the county clerk to properly record or index a filed
    > affidavit does not invalidate the lien.
    > § 53.053. Accrual of Indebtedness
    >
    >
    > (a) For purposes of Section 53.052, indebtedness accrues on a
    > contract under which a plan or plat is prepared, labor was
    > performed, materials furnished, or specially fabricated materials
    > are to be furnished in accordance with this section.
    >
    > (b) Indebtedness to an original contractor accrues:
    >
    > (1) on the last day of the month in which a written declaration by
    > the original contractor or the owner is received by the other party
    > to the original contract stating that the original contract has been
    > terminated; or
    >
    > (2) on the last day of the month in which the original contract has
    > been completed, finally settled, or abandoned.
    >
    > (c) Indebtedness to a subcontractor, or to any person not covered by
    > Subsection (b) or (d), who has furnished labor or material to an
    > original contractor or to another subcontractor accrues on the last
    > day of the last month in which the labor was performed or the
    > material furnished.
    >
    > (d) Indebtedness for specially fabricated material accrues:
    >
    > (1) on the last day of the last month in which materials were
    > delivered;
    >
    > (2) on the last day of the last month in which delivery of the last
    > of the material would normally have been required at the job site;
    > or
    >
    > (3) on the last day of the month of any material breach or
    > termination of the original contract by the owner or contractor or
    > of the subcontract under which the specially fabricated material was
    > furnished.
    >
    > (e) A claim for retainage accrues on the last day of the month in
    > which all work called for by the contract between the owner and the
    > original contractor has been completed, finally settled, or
    > abandoned.
    > § 53.054. Contents of Affidavit
    >
    >
    > (a) The affidavit must be signed by the person claiming the lien or
    > by another person on the claimant's behalf and must contain
    > substantially:
    >
    > (1) a sworn statement of the amount of the claim;
    >
    > (2) the name and last known address of the owner or reputed owner;
    >
    > (3) a general statement of the kind of work done and materials
    > furnished by the claimant and, for a claimant other than an original
    > contractor, a statement of each month in which the work was done and
    > materials furnished for which payment is requested;
    >
    > (4) the name and last known address of the person by whom the
    > claimant was employed or to whom the claimant furnished the
    > materials or labor;
    >
    > (5) the name and last known address of the original contractor;
    >
    > (6) a description, legally sufficient for identification, of the
    > property sought to be charged with the lien;
    >
    > (7) the claimant's name, mailing address, and, if different,
    > physical address; and
    >
    > (8) for a claimant other than an original contractor, a statement
    > identifying the date each notice of the claim was sent to the owner
    > and the method by which the notice was sent.
    >
    > (b) The claimant may attach to the affidavit a copy of any
    > applicable written agreement or contract and a copy of each notice
    > sent to the owner.
    >
    > (c) The affidavit is not required to set forth individual items of
    > work done or material furnished or specially fabricated.
    >
    > The affidavit may use any abbreviations or symbols customary in the
    > trade.
    > § 53.055. Notice of Filed Affidavit
    >
    >
    > (a) A person who files an affidavit must send a copy of the
    > affidavit by registered or certified mail to the owner or reputed
    > owner at the owner's last known business or residence address not
    > later than the fifth day after the date the affidavit is filed with
    > the county clerk.
    >
    > (b) If the person is not an original contractor, the person must
    > also send a copy of the affidavit to the original contractor at the
    > original contractor's last known business or residence address
    > within the same period.
    > § 53.056. Derivative Claimant: Notice to Owner or Original
    > Contractor
    >
    >
    > (a) Except as provided by Subchapter K, [FN1] a claimant other than
    > an original contractor must give the notice prescribed by this
    > section for the lien to be valid.
    >
    > (b) If the lien claim arises from a debt incurred by a
    > subcontractor, the claimant must give to the original contractor
    > written notice of the unpaid balance. The claimant must give the
    > notice not later than the 15th day of the second month following
    > each month in which all or part of the claimant's labor was
    > performed or material delivered. The claimant must give the same
    > notice to the owner or reputed owner and the original contractor not
    > later than the 15th day of the third month following each month in
    > which all or part of the claimant's labor was performed or material
    > or specially fabricated material was delivered.
    >
    > (c) If the lien claim arises from a debt incurred by the original
    > contractor, the claimant must give notice to the owner or reputed
    > owner, with a copy to the original contractor, in accordance with
    > Subsection (b).
    >
    > (d) To authorize the owner to withhold funds under Subchapter D,
    > [FN2] the notice to the owner must state that if the claim remains
    > unpaid, the owner may be personally liable and the owner's property
    > may be subjected to a lien unless:
    >
    > (1) the owner withholds payments from the contractor for payment of
    > the claim; or
    >
    > (2) the claim is otherwise paid or settled.
    >
    > (e) The notice must be sent by registered or certified mail and must
    > be addressed to the owner or reputed owner or the original
    > contractor, as applicable, at his last known business or residence
    > address.
    >
    > (f) A copy of the statement or billing in the usual and customary
    > form is sufficient as notice under this section.
    > § 53.057. Derivative Claimant: Notice for Contractual Retainage
    > Claim
    >
    >
    > (a) A claimant may give notice under this section instead of or in
    > addition to notice under Section 53.056 or 53.252 if the claimant is
    > to labor, furnish labor or materials, or specially fabricate
    > materials under an agreement with an original contractor or a
    > subcontractor providing for retainage.
    >
    > (b) The claimant must give the owner or reputed owner notice of the
    > retainage agreement not later than the 15th day of the second month
    > following the delivery of materials or the performance of labor by
    > the claimant that first occurs after the claimant has agreed to the
    > contractual retainage. If the agreement is with a subcontractor, the
    > claimant must also give notice within that time to the original
    > contractor.
    >
    > (c) The notice must contain:
    >
    > (1) the sum to be retained;
    >
    > (2) the due date or dates, if known; and
    >
    > (3) a general indication of the nature of the agreement.
    >
    > (d) The notice must be sent by registered or certified mail to the
    > last known business or residence address of the owner or reputed
    > owner or the original contractor, as applicable.
    >
    > (e) If a claimant gives notice under this section and Section 53.055
    > or, if the claim relates to a residential construction project,
    > under this section and Section 53.252, the claimant is not required
    > to give any other notice as to the retainage.
    > § 53.058. Derivative Claimant: Notice for Specially Fabricated Items
    >
    >
    > (a) Except as provided by Subchapter K, [FN1] a claimant who
    > specially fabricates material must give notice under this section
    > for the lien to be valid.
    >
    > (b) The claimant must give the owner or reputed owner notice not
    > later than the 15th day of the second month after the month in which
    > the claimant receives and accepts the order for the material. If the
    > indebtedness is incurred by a person other than the original
    > contractor, the claimant must also give notice within that time to
    > the original contractor.
    >
    > (c) The notice must contain:
    >
    > (1) a statement that the order has been received and accepted; and
    >
    > (2) the price of the order.
    >
    > (d) The notice must be sent by registered or certified mail to the
    > last known business or residence address of the owner or the reputed
    > owner or the original contractor, as applicable.
    > (e) In addition to notice under this section, the claimant must give
    > notice under Section 53.056 if delivery has been made or if the
    > normal delivery time for the job has passed.
    >
    >
    > (f) The lien of a claimant who accepts an order but fails to give
    > notice under this section is valid as to delivered items if the
    > claimant has given notice under Section 53.056.
    >
    > (g) If a retainage agreement consists in whole or part of an
    > obligation to furnish specially fabricated materials and the
    > claimant has given notice under Section 53.057, the claimant is not
    > required to give notice under this section.
    > § 53.059. Repealed by Acts 1997, 75th Leg., ch. 526, § 24, eff.
    > Sept. 1, 1997
    >
    > [Sections 53.060 to 53.080 reserved for expansion]
    >
    > SUBCHAPTER D FUNDS WITHHELD BY OWNER FOLLOWING NOTICE
    >
    > § 53.081. Authority to Withhold Funds for Benefit of Claimants
    >
    >
    > (a) If an owner receives notice under Section 53.056, 53.057,
    > 53.058, 53.252, or 53.253, the owner may withhold from payments to
    > the original contractor an amount necessary to pay the claim for
    > which he receives notice.
    >
    > (b) If notice is sent in a form that substantially complies with
    > Section 53.056 or 53.252, the owner may withhold the funds
    > immediately on receipt of the notice.
    >
    > (c) If notice is sent under Section 53.057, the owner may withhold
    > funds immediately on receipt of a copy of the claimant's affidavit
    > prepared in accordance with Sections 53.052 through 53.055.
    >
    > (d) If notice is sent under Section 53.058, the owner may withhold
    > funds immediately on receipt of the notices sent under Subsection
    > (e) of that section. If notice is sent as provided by Section 53.253
    > (b), the owner may withhold funds immediately on receipt of the
    > notice sent as required by Section 53.252.
    > § 53.082. Time for Which Funds are Withheld
    >
    >
    > Unless payment is made under Section 53.083 or the claim is
    > otherwise settled, discharged, indemnified against under Subchapter
    > H or I, [FN1] or determined to be invalid by a final judgment of a
    > court, the owner shall retain the funds withheld until:
    >
    > (1) the time for filing the affidavit of mechanic's lien has passed;
    > or
    >
    > (2) if a lien affidavit has been filed, until the lien claim has
    > been satisfied or released.
    > § 53.083. Payment to Claimant on Demand
    >
    >
    > (a) The claimant may make written demand for payment of the claim to
    > an owner authorized to withhold funds under this subchapter. The
    > demand must give notice to the owner that all or part of the claim
    > has accrued under Section 53.053 or is past due according to the
    > agreement between the parties.
    >
    > (b) The claimant must send a copy of the demand to the original
    > contractor. The original contractor may give the owner written
    > notice that the contractor intends to dispute the claim. The
    > original contractor must give the notice not later than the 30th day
    > after the day he receives the copy of the demand. If the original
    > contractor does not give the owner timely notice, he is considered
    > to have assented to the demand and the owner shall pay the claim.
    >
    > (c) The claimant's demand may accompany the original notice of
    > nonpayment or of a past-due claim and may be stamped or written in
    > legible form on the face of the notice.
    >
    > (d) Unless the lien has been secured, the demand may not be made
    > after expiration of the time within which the claimant may secure
    > the lien for the claim.
    > § 53.084. Owner's Liability
    >
    >
    > (a) Except for the amount required to be retained under Subchapter
    > E, [FN1] the owner is not liable for any amount paid to the original
    > contractor before the owner is authorized to withhold funds under
    > this subchapter.
    >
    > (b) If the owner has received the notices required by Subchapter C
    > [FN2] or K, [FN3] if the lien has been secured, and if the claim has
    > been reduced to final judgment, the owner is liable and the owner's
    > property is subject to a claim for any money paid to the original
    > contractor after the owner was authorized to withhold funds under
    > this subchapter. The owner is liable for that amount in addition to
    > any amount for which he is liable under Subchapter E.
    > § 53.085. Affidavit Required
    >
    >
    > (a) Any person who furnishes labor or materials for the construction
    > of improvements on real property shall, if requested and as a
    > condition of payment for such labor or materials, provide to the
    > requesting party, or the party's agent, an affidavit stating that
    > the person has paid each of the person's subcontractors, laborers,
    > or materialmen in full for all labor and materials provided to the
    > person for the construction. In the event, however, that the person
    > has not paid each of the person's subcontractors, laborers, or
    > materialmen in full, the person shall state in the affidavit the
    > amount owed and the name and, if known, the address and telephone
    > number of each subcontractor, laborer, or materialman to whom the
    > payment is owed.
    >
    > (b) The seller of any real property shall, upon request by the
    > purchaser or the purchaser's agent prior to closing of the purchase
    > of the real property, provide to the purchaser or the purchaser's
    > agent, a written affidavit stating that the seller has paid each of
    > the seller's contractors, laborers, or materialmen in full for all
    > labor and materials provided to the seller through the date
    > specified in the affidavit for any construction of improvements on
    > the real property and that the seller is not indebted to any person,
    > firm, or corporation by reason of any such construction through the
    > date specified in the affidavit. In the event that the seller has
    > not paid each of the seller's contractors, laborers, or materialmen
    > in full for labor and material provided through the date specified
    > in the affidavit, the seller shall state in the affidavit the amount
    > owed and the name and, if known, the address and telephone number of
    > each contractor, laborer, or materialman to whom the payment is
    > owed.
    >
    > (c) The affidavit may include:
    >
    > (1) a waiver or release of lien rights by the affiant that is
    > conditioned on the receipt of actual payment or collection of funds
    > when payment is made by check or draft;
    >
    > (2) a warranty or representation that certain bills or classes of
    > bills will be paid by the affiant from funds paid in reliance on the
    > affidavit; and
    >
    > (3) an indemnification by the affiant for any loss or expense
    > resulting from false or incorrect information in the affidavit.
    >
    > (d) A person, including a seller, commits an offense if the person
    > intentionally, knowingly, or recklessly makes a false or misleading
    > statement in an affidavit under this section. An offense under this
    > section is a misdemeanor. A person adjudged guilty of an offense
    > under this section shall be punished by a fine not to exceed $4,000
    > or confinement in jail for a term not to exceed one year or both a
    > fine and confinement. A person may not receive community supervision
    > for the offense.
    >
    > (e) A person signing an affidavit under this section is personally
    > liable for any loss or damage resulting from any false or incorrect
    > information in the affidavit.
    > [Sections 53.086 to 53.100 reserved for expansion]
    >
    > SUBCHAPTER E REQUIRED RETAINAGE FOR BENEFIT OF LIEN CLAIMANTS
    >
    > § 53.101. Required Retainage
    >
    >
    > (a) During the progress of work under an original contract for which
    > a mechanic's lien may be claimed and for 30 days after the work is
    > completed, the owner shall retain:
    >
    > (1) 10 percent of the contract price of the work to the owner; or
    >
    > (2) 10 percent of the value of the work, measured by the proportion
    > that the work done bears to the work to be done, using the contract
    > price or, if there is no contract price, using the reasonable value
    > of the completed work.
    >
    > (b) In this section, "owner" includes the owner's agent, trustee, or
    > receiver.
    > § 53.102. Payment Secured by Retainage
    >
    >
    > The retained funds secure the payment of artisans and mechanics who
    > perform labor or service and the payment of other persons who
    > furnish material, material and labor, or specially fabricated
    > material for any contractor, subcontractor, agent, or receiver in
    > the performance of the work.
    > § 53.103. Lien on Retained Funds
    >
    >
    > A claimant has a lien on the retained funds if the claimant:
    >
    > (1) sends the notices required by this chapter in the time and
    > manner required; and
    >
    > (2) files an affidavit claiming a lien not later than the 30th day
    > after the work is completed.
    > § 53.104. Preferences
    >
    >
    > (a) Individual artisans and mechanics are entitled to a preference
    > to the retained funds and shall share proportionately to the extent
    > of their claims for wages and fringe benefits earned.
    >
    > (b) After payment of artisans and mechanics who are entitled to a
    > preference under Subsection (a), other participating claimants share
    > proportionately in the balance of the retained funds.
    > § 53.105. Owner's Liability for Failure to Retain
    >
    >
    > (a) If the owner fails or refuses to comply with this subchapter,
    > the claimants complying with this chapter have a lien, at least to
    > the extent of the amount that should have been retained from the
    > original contract under which they are claiming, against the house,
    > building, structure, fixture, or improvement and all of its
    > properties and against the lot or lots of land necessarily
    > connected.
    >
    > (b) The claimants share the lien proportionately in accordance with
    > the preference provided by Section 53.104.
    > § 53.106. Affidavit of Completion
    >
    >
    > (a) An owner may file with the county clerk of the county in which
    > the property is located an affidavit of completion. The affidavit
    > must contain:
    >
    > (1) the name and address of the owner;
    >
    > (2) the name and address of the original contractor;
    >
    > (3) a description, legally sufficient for identification, of the
    > real property on which the improvements are located;
    >
    > (4) a description of the improvements furnished under the original
    > contract;
    >
    > (5) a statement that the improvements under the original contract
    > have been completed and the date of completion; and
    >
    > (6) a conspicuous statement that a claimant may not have a lien on
    > retained funds unless the claimant files the affidavit claiming a
    > lien not later than the 30th day after the date of completion.
    >
    > (b) A copy of the affidavit must be sent by certified or registered
    > mail to the original contractor not later than the date the
    > affidavit is filed and to each claimant who sends a notice of lien
    > liability to the owner under Section 53.056, 53.057, 53.058, 53.252,
    > or 53.253 not later than the date the affidavit is filed or the 10th
    > day after the date the owner receives the notice of lien liability,
    > whichever is later.
    >
    > (c) A copy of the affidavit must also be sent to each person who
    > furnishes labor or materials for the property and who furnishes the
    > owner with a written request for the copy. The owner must furnish
    > the copy to the person not later than the date the affidavit is
    > filed or the 10th day after the date the request is received,
    > whichever is later.
    >
    > (d) Except as provided by this subsection, an affidavit filed under
    > this section on or before the 10th day after the date of completion
    > of the improvements is prima facie evidence of the date the work
    > under the original contract is completed for purposes of this
    > subchapter. If the affidavit is filed after the 10th day after the
    > date of completion, the date of completion for purposes of this
    > subchapter is the date the affidavit is filed. This subsection does
    > not apply to a person to whom the affidavit was not sent as required
    > by this section.
    >
    > (e) Repealed by Acts 1999, 76th Leg., ch. 889, § 12, eff. Sept. 1,
    > 1999.
    > [Sections 53.107 to 53.120 reserved for expansion]
    >
    > SUBCHAPTER F PRIORITIES AND PREFERENCES
    >
    > § 53.121. Preference Over Other Creditors
    >
    >
    > All subcontractors, laborers, and materialmen who have a mechanic's
    > lien have preference over other creditors of the original
    > contractor.
    > § 53.122. Equality of Mechanic's Liens
    >
    >
    > (a) Except as provided by Subchapter E [FN1] and Section 53.124(e),
    > perfected mechanic's liens are on equal footing without reference to
    > the date of filing the affidavit claiming the lien.
    >
    > (b) If the proceeds of a foreclosure sale of property are
    > insufficient to discharge all mechanic's liens against the property,
    > the proceeds shall be paid pro rata on the perfected mechanic's
    > liens on which suit is brought.
    >
    > (c) This chapter does not affect the contract between the owner and
    > the original contractor as to the amount, manner, or time of payment
    > of the contract price.
    > § 53.123. Priority of Mechanic's Lien Over Other Liens
    >
    >
    > (a) Except as provided by this section, a mechanic's lien attaches
    > to the house, building, improvements, or railroad property in
    > preference to any prior lien, encumbrance, or mortgage on the land
    > on which it is located, and the person enforcing the lien may have
    > the house, building, improvement, or any piece of the railroad
    > property sold separately.
    >
    > (b) The mechanic's lien does not affect any lien, encumbrance, or
    > mortgage on the land or improvement at the time of the inception of
    > the mechanic's lien, and the holder of the lien, encumbrance, or
    > mortgage need not be made a party to a suit to foreclose the
    > mechanic's lien.
    > § 53.124. Inception of Mechanic's Lien
    >
    >
    > (a) Except as provided by Subsection (e), for purposes of Section
    > 53.123, the time of inception of a mechanic's lien is the
    > commencement of construction of improvements or delivery of
    > materials to the land on which the improvements are to be located
    > and on which the materials are to be used.
    >
    > (b) The construction or materials under Subsection (a) must be
    > visible from inspection of the land on which the improvements are
    > being made.
    >
    > (c) An owner and original contractor may jointly file an affidavit
    > of commencement with the county clerk of the county in which the
    > land is located not later than the 30th day after the date of actual
    > commencement of construction of the improvements or delivery of
    > materials to the land. The affidavit must contain:
    >
    > (1) the name and address of the owner;
    >
    > (2) the name and address of each original contractor, known at the
    > time to the owner, that is furnishing labor, service, or materials
    > for the construction of the improvements;
    >
    > (3) a description, legally sufficient for identification, of the
    > property being improved;
    >
    > (4) the date the work actually commenced; and
    >
    > (5) a general description of the improvement.
    >
    > (d) An affidavit filed in compliance with this section is prima
    > facie evidence of the date of the commencement of the improvement
    > described in the affidavit. The time of inception of a mechanic's
    > lien arising from work described in an affidavit of commencement is
    > the date of commencement of the work stated in the affidavit.
    >
    > (e) The time of inception of a lien that is created under Section
    > 53.021(c) or (d) is the date of recording of an affidavit of lien
    > under Section 53.052. The priority of a lien claimed by a person
    > entitled to a lien under Section 53.021(c) or (d) with respect to
    > other mechanic's liens is determined by the date of recording. A
    > lien created under Section 53.021(c) or (d) is not valid or
    > enforceable against a grantee or purchaser who acquires an interest
    > in the real property before the time of inception of the lien.
    > [Sections 53.125 to 53.150 reserved for expansion]
    >
    > SUBCHAPTER G RELEASE AND FORECLOSURE; ACTION ON CLAIM TEXAS PROPERTY
    >
    > § 53.151. Enforcement of Remedies Against Money Due Original
    > Contractor or Subcontractor
    >
    >
    > (a) A creditor of an original contractor may not collect, enforce a
    > security interest against, garnish, or levy execution on the money
    > due the original contractor or the contractor's surety from the
    > owner, and a creditor of a subcontractor may not collect, enforce a
    > security interest against, garnish, or levy execution on the money
    > due the subcontractor, to the prejudice of the subcontractors,
    > mechanics, laborers, materialmen, or their sureties.
    >
    > (b) A surety issuing a payment bond or performance bond in
    > connection with the improvements has a priority claim over other
    > creditors of its principal to contract funds to the extent of any
    > loss it suffers or incurs. That priority does not excuse the surety
    > from paying any obligations that it may have under its payment
    > bonds.
    > § 53.152. Release of Claim or Lien
    >
    >
    > (a) When a debt for labor or materials is satisfied or paid by
    > collected funds, the person who furnished the labor or materials
    > shall, not later than the 10th day after the date of receipt of a
    > written request, furnish to the requesting person a release of the
    > indebtedness and any lien claimed, to the extent of the indebtedness
    > paid. An owner, the original contractor, or any person making the
    > payment may request the release.
    >
    > (b) A release of lien must be in a form that would permit it to be
    > filed of record.
    > § 53.153. Defense of Actions
    >
    >
    > (a) If an affidavit claiming a mechanic's lien is filed by a person
    > other than the original contractor, the original contractor shall
    > defend at his own expense a suit brought on the claim.
    >
    > (b) If the suit results in judgment on the lien against the owner or
    > the owner's property, the owner is entitled to deduct the amount of
    > the judgment and costs from any amount due the original contractor.
    > If the owner has settled with the original contractor in full, the
    > owner is entitled to recover from the original contractor any amount
    > paid for which the original contractor was originally liable.
    > § 53.154. Foreclosure
    >
    >
    > A mechanic's lien may be foreclosed only on judgment of a court of
    > competent jurisdiction foreclosing the lien and ordering the sale of
    > the property subject to the lien.
    > § 53.155. Transfer of Property Sold
    >
    >
    > If the house, building, improvement, or any piece of railroad
    > property is sold separately, the officer making the sale shall place
    > the purchaser in possession. The purchaser is entitled to a
    > reasonable time after the date of purchase within which to remove
    > the purchased property.
    > § 53.156. Costs and Attorney's Fees
    >
    >
    > In any proceeding to foreclose a lien or to enforce a claim against
    > a bond issued under Subchapter H, I, or J [FN1] or in any proceeding
    > to declare that any lien or claim is invalid or unenforceable in
    > whole or in part, the court may award costs and reasonable
    > attorney's fees as are equitable and just.
    > § 53.157. Discharge of Lien
    >
    >
    > A mechanic's lien or affidavit claiming a mechanic's lien filed
    > under Section 53.052 may be discharged of record by:
    >
    > (1) recording a lien release signed by the claimant under Section
    > 53.152;
    >
    > (2) failing to institute suit to foreclose the lien in the county in
    > which the property is located within the period prescribed by
    > Section 53.158, 53.175, or 53.208;
    >
    > (3) recording the original or certified copy of a final judgment or
    > decree of a court of competent jurisdiction providing for the
    > discharge;
    >
    > (4) filing the bond and notice in compliance with Subchapter H;
    > [FN1]
    >
    > (5) filing the bond in compliance with Subchapter I; [FN2] or
    >
    > § 53.158. Period for Bringing Suit to Foreclose Lien
    >
    > (a) Except as provided by Subsection (b), suit must be brought to
    > foreclose the lien within two years after the last day a claimant
    > may file the lien affidavit under Section 53.052 or within one year
    > after completion, termination, or abandonment of the work under the
    > original contract under which the lien is claimed, whichever is
    > later.
    >
    > (b) For a claim arising from a residential construction project,
    > suit must be brought to foreclose the lien within one year after the
    > last day a claimant may file a lien affidavit under Section 53.052
    > or within one year after completion, termination, or abandonment of
    > the work under the original contract under which the lien is
    > claimed, whichever is later.
    >
    >
    > On 3/15/05, v wrote:
    >> Have you checked the revised
    >> codes? Joisey is two years. Used to
    >> be 20. With the option to renew the
    >> lien in the twenyfirst year. Then
    >> it ran till paid.
    >>
    >>
    >> On 3/15/05, roosta wrote:
    >>> On 3/15/05, Curmudgeon wrote:
    >>>> Perhaps someone can pitch in if
    >> there is some peculiarity in
    >>>> Texas law. The general rule is
    >> that mechanics liens expire
    >>>> after one year if they are not
    >> foreclosed. In other words,
    >>>> you can't just sit on it. You
    >> either foreclose or lose the
    >>>> lien.
    >>>
    >> http://www.capitol.state.tx.us/statu
    >> tes/pr.toc.htm
    >>> PROPERTY CODE
    >>> Title 5
    >>> CHAPTER 53. MECHANIC'S,
    >> CONTRACTOR'S, OR MATERIALMAN'S LIEN

    Posts on this thread, including this one
  • machenics lein / texas, 3/15/05, by debi zerby.
  • Re: machenics lein / texas, 3/15/05, by roosta.
  • Re: machenics lein / texas, 3/15/05, by Curmudgeon.
  • Re: machenics lein / texas, 3/15/05, by roosta.
  • Re: machenics lein / texas Roo, 3/15/05, by v.
  • Re: machenics lein / texas Roo, 3/15/05, by Curmudgeon.
  • Re: machenics lein / texas Roo, 3/15/05, by Curmudgeon---Don't Open My Last Post.
  • Re: machenics lein / Time out for Mudge, 3/15/05, by v.
  • Re: machenics lein last post, 3/15/05, by roosta.
  • Re: machenics lein last post Roo, 3/15/05, by v.
  • Re: machenics lein last post Roo, 3/16/05, by Michael.
  • Re: machenics lein last post Mikey, 3/16/05, by roosta.
  • Re: machenics lein last post Roo, 3/16/05, by Michael.
  • Re: machenics lein last post Roo, 3/16/05, by v.
  • Re: machenics lein last post V, 3/17/05, by Michael.


  Site Map:  Home Chatboards Legal Jobs Classified Ads Search Contacts Advertise
  © 1996 - 2013. All Rights Reserved. Please review our Terms of Use, Mission Statement, and Privacy Policy.