I am building a house in louisiana. Way back in September of 2003, I paid for a total package for my house slab. The contract included all material and labor for a complete job. The work was performed and I paid the bill upon completion. Now six months later, I get a notice from the company that supplied the concrete for the job saying that their bill has not been paid and that they are going to place a lein on my house. I did not request this concrete from the supplier nor did I enter into contract with this supplier yet the lein is going to be placed on my house by the supplier. What can I do? Is this how the law works in Louisiana? Is there something that is not being told to me? Any help would be appreciated.
Posts on this thread, including this one
- lein, 3/17/04, by trey dugas.
- Re: lein, 3/17/04, by Kibitzer.
|