Follow us!

    Re: machenics lein / texas Roo

    Posted by Curmudgeon on 3/15/05

    TEXAS PROPERTY CODE
    [Mechanic's Lien Statutes in effect as of August 1, 2003]
    [Does not include any changes which may become effective at a later
    date]

    CHAPTER 53. MECHANIC'S, CONTRACTOR'S, OR MATERIALMAN'S LIEN

    TABLE OF CONTENTS

    SUBCHAPTER A. GENERAL PROVISIONS


    § 53.001. Definitions

    § 53.002. More Than One Original Contractor

    § 53.003. Notices"

    § 53.004. reserved for expansion

    § 53.020. reserved for expansion
    SUBCHAPTER B PERSONS ENTITLED TO LIEN; SUBJECT PROPERTY


    § 53.021. Persons Entitled to Lien

    § 53.022. Property to Which Lien Extends

    § 53.023. Payment Secured by Lien

    § 53.024. Limitation on Subcontractor's Lien

    § 53.025. Limitation on Ordinary Retainage Lien

    § 53.026. Sham Contract

    § 53.027. reserved for expansion

    § 53.028. reserved for expansion
    SUBCHAPTER C PROCEDURE FOR PERFECTING LIEN


    § 53.051. Necessary Procedures

    § 53.052. Filing of Affidavit

    § 53.053. Accrual of Indebtedness

    § 53.054. Contents of Affidavit

    § 53.055. Notice of Filed Affidavit

    § 53.056. Derivative Claimant: Notice to Owner or Original
    Contractor

    § 53.057. Derivative Claimant: Notice for Contractual Retainage
    Claim

    § 53.058. Derivative Claimant: Notice for Specially Fabricated Items

    § 53.059. Repealed by Acts 1997, 75th Leg., ch. 526, s 24, eff.
    Sept. 1, 1997

    § 53.060. reserved for expansion

    § 53.080. reserved for expansion
    SUBCHAPTER D FUNDS WITHHELD BY OWNER FOLLOWING NOTICE


    § 53.081. Authority to Withhold Funds for Benefit of Claimants

    § 53.082. Time for Which Funds are Withheld

    § 53.083. Payment to Claimant on Demand

    § 53.084. Owner's Liability

    § 53.085. Affidavit Required

    § 53.086. reserved for expansion

    § 53.100. reserved for expansion
    SUBCHAPTER E REQUIRED RETAINAGE FOR BENEFIT OF LIEN CLAIMANTS


    § 53.101. Required Retainage

    § 53.102. Payment Secured by Retainage

    § 53.103. Lien on Retained Funds

    § 53.104. Preferences

    § 53.105. Owner's Liability for Failure to Retain

    § 53.106. Affidavit of Completion

    § 53.107. reserved for expansion

    § 53.120. reserved for expansion
    SUBCHAPTER F PRIORITIES AND PREFERENCES


    § 53.121. Preference Over Other Creditors

    § 53.122. Equality of Mechanic's Liens

    § 53.123. Priority of Mechanic's Lien Over Other Liens

    § 53.124. Inception of Mechanic's Lien

    § 53.125. reserved for expansion

    § 53.150. reserved for expansion
    SUBCHAPTER G RELEASE AND FORECLOSURE; ACTION ON CLAIM


    § 53.151. Enforcement of Remedies Against Money Due Original
    Contractor

    or Subcontractor

    § 53.152. Release of Claim or Lien

    § 53.153. Defense of Actions

    § 53.154. Foreclosure

    § 53.155. Transfer of Property Sold

    § 53.156. Costs and Attorney's Fees

    § 53.157. Discharge of Lien

    § 53.158. Period for Bringing Suit to Foreclose Lien

    § 53.159. Obligation to Furnish Information

    § 53.160. Summary Motion to Remove Invalid or Unenforceable Lien

    § 53.161. Bond Requirements After Order to Remove

    § 53.162. Revival of Removed Lien

    § 53.163. reserved for expansion

    § 53.170. reserved for expansion
    SUBCHAPTER H BOND TO INDEMNIFY AGAINST LIEN


    § 53.171. Bond

    § 53.172. Bond Requirements

    § 53.173. Notice of Bond

    § 53.174. Recording of Bond and Notice

    § 53.175. Action on Bond

    § 53.176. Repealed by Acts 1989, 71st Leg., ch. 1138, s 39(2), eff.
    Sept. 1, 1989

    § 53.177. reserved for expansion

    § 53.200. reserved for expansion
    SUBCHAPTER I BOND TO PAY LIENS OR CLAIMS


    § 53.201. Bond

    § 53.202. Bond Requirements

    § 53.203. Recording of Bond and Contract

    § 53.204. Reliance on Record

    § 53.205. Enforceable Claims

    § 53.206. Perfection of Claim

    § 53.207. Owner's Notice of Claim to Surety

    § 53.208. Action on Bond

    § 53.209. Repealed by Acts 1989, 71st Leg., ch. 1138, s 39(3), eff.
    Sept. 1, 1989

    § 53.210. Claims in Excess of Bond Amount

    § 53.211. Attempted Compliance

    § 53.212. reserved for expansion

    § 53.230. reserved for expansion
    SUBCHAPTER J LIEN ON MONEY DUE PUBLIC WORKS CONTRACTOR


    § 53.231. Lien

    § 53.232. To Whom Notice Given; Manner

    § 53.233. Contents of Notice

    § 53.234. Time for Notice

    § 53.235. Official to Retain Funds

    § 53.236. Bond for Release of Lien

    § 53.237. Bond Requirements

    § 53.238. Notice of Bond

    § 53.239. Action on Bond

    § 53.240. Repealed by Acts 1989, 71st Leg., ch. 1138, s 39(4), eff.
    Sept. 1, 1989
    SUBCHAPTER K RESIDENTIAL CONSTRUCTION PROJECTS


    § 53.251. Procedures for Residential Construction Projects

    § 53.252. Derivative Claimant: Notice to Owner or Original
    Contractor

    § 53.253. Derivative Claimant: Notice for Specially Fabricated Items

    § 53.254. Homestead

    § 53.255. Disclosure Statement Required for Residential Construction
    Contract

    § 53.256. List of Subcontractors and Suppliers

    § 53.257. Provisions Related to Closing of Loan for Construction of
    Improvements

    § 53.258. Disbursements of Funds

    § 53.259. Final Bills-Paid Affidavit Required

    § 53.260. Conveyance to Contractor Not Required

    CHAPTER 53. MECHANIC'S, CONTRACTOR'S, OR MATERIALMAN'S LIEN


    SUBCHAPTER A. GENERAL PROVISIONS

    § 53.001. Definitions

    In this chapter:


    (1) "Contract price" means the cost to the owner for any part of
    construction or repair performed under an original contract.

    (2) "Improvement" includes:

    (A) abutting sidewalks and streets and utilities in or on those
    sidewalks and streets;

    (B) clearing, grubbing, draining, or fencing of land;

    (C) wells, cisterns, tanks, reservoirs, or artificial lakes or pools
    made for supplying or storing water;

    (D) pumps, siphons, and windmills or other machinery or apparatuses
    used for raising water for stock, domestic use, or irrigation; and

    (E) planting orchard trees, grubbing out orchards and replacing
    trees, and pruning of orchard trees.

    (3) "Labor" means labor used in the direct prosecution of the work.

    (4) "Material" means all or part of:

    (A) the material, machinery, fixtures, or tools incorporated into
    the work, consumed in the direct prosecution of the work, or ordered
    and delivered for incorporation or consumption;

    (B) rent at a reasonable rate and actual running repairs at a
    reasonable cost for construction equipment used or reasonably
    required and delivered for use in the direct prosecution of the work
    at the site of the construction or repair; or

    (C) power, water, fuel, and lubricants consumed or ordered and
    delivered for consumption in the direct prosecution of the work.

    (5) "Mechanic's lien" means the lien provided by this chapter.

    (6) "Original contract" means an agreement to which an owner is a
    party either directly or by implication of law.

    (7) "Original contractor" means a person contracting with an owner
    either directly or through the owner's agent.

    (8) "Residence" means a single-family house, duplex, triplex, or
    quadruplex or a unit in a multiunit structure used for residential
    purposes that is:

    (A) owned by one or more adult persons; and (B) used or intended to
    be used as a dwelling by one of the owners.

    (9) "Residential construction contract" means a contract between an
    owner and a contractor in which the contractor agrees to construct
    or repair the owner's residence, including improvements appurtenant
    to the residence.

    (10) "Residential construction project" means a project for the
    construction or repair of a new or existing residence, including
    improvements appurtenant to the residence, as provided by a
    residential construction contract.

    (11) "Retainage" means an amount representing part of a contract
    payment that is not required to be paid to the claimant within the
    month following the month in which labor is performed, material is
    furnished, or specially fabricated material is delivered. The term
    does not include retainage under Subchapter E. [FN1]

    (12) "Specially fabricated material" means material fabricated for
    use as a component of the construction or repair so as to be
    reasonably unsuitable for use elsewhere.

    (13) "Subcontractor" means a person who has furnished labor or
    materials to fulfill an obligation to an original contractor or to a
    subcontractor to perform all or part of the work required by an
    original contract.

    (14) "Work" means any part of construction or repair performed under
    an original contract.

    (15) "Completion" of an original contract means the actual
    completion of the work, including any extras or change orders
    reasonably required or contemplated under the original contract,
    other than warranty work or replacement or repair of the work
    performed under the contract.
    § 53.002. More Than One Original Contractor

    On any work there may be more than one original contractor for
    purposes of this chapter.

    § 53.003. Notices


    (a) This section applies to notices required by Subchapters B
    through G and K. [FN1]

    (b) Any notice or other written communication may be delivered in
    person to the party entitled to the notice or to that party's agent,
    regardless of the manner prescribed by law.

    (c) If notice is sent by registered or certified mail, deposit or
    mailing of the notice in the United States mail in the form required
    constitutes compliance with the notice requirement. This subsection
    does not apply if the law requires receipt of the notice by the
    person to whom it is directed.

    (d) If a written notice is received by the person entitled to
    receive it, the method by which the notice was delivered is
    immaterial.
    [Sections 53.004 to 53.020 reserved for expansion]

    SUBCHAPTER B PERSONS ENTITLED TO LIEN; SUBJECT PROPERTY

    § 53.021. Persons Entitled to Lien


    (a) A person has a lien if:

    (1) the person labors, specially fabricates material, or furnishes
    labor or materials for construction or repair in this state of:

    (A) a house, building, or improvement;

    (B) a levee or embankment to be erected for the reclamation of
    overflow land along a river or creek; or

    (C) a railroad; and

    (2) the person labors, specially fabricates the material, or
    furnishes the labor or materials under or by virtue of a contract
    with the owner or the owner's agent, trustee, receiver, contractor,
    or subcontractor.

    (b) A person who specially fabricates material has a lien even if
    the material is not delivered.

    (c) An architect, engineer, or surveyor who prepares a plan or plat
    under or by virtue of a written contract with the owner or the
    owner's agent, trustee, or receiver in connection with the actual or
    proposed design, construction, or repair of improvements on real
    property or the location of the boundaries of real property has a
    lien on the property.

    (d) A person who provides labor, plant material, or other supplies
    for the installation of landscaping for a house, building, or
    improvement, including the construction of a retention pond,
    retaining wall, berm, irrigation system, fountain, or other similar
    installation, under or by virtue of a written contract with the
    owner or the owner's agent, trustee, or receiver has a lien on the
    property.
    § 53.022. Property to Which Lien Extends


    (a) The lien extends to the house, building, fixtures, or
    improvements, the land reclaimed from overflow, or the railroad and
    all of its properties, and to each lot of land necessarily connected
    or reclaimed.

    (b) The lien does not extend to abutting sidewalks, streets, and
    utilities that are public property.

    (c) A lien against land in a city, town, or village extends to each
    lot on which the house, building, or improvement is situated or on
    which the labor was performed.

    (d) A lien against land not in a city, town, or village extends to
    not more than 50 acres on which the house, building, or improvement
    is situated or on which the labor was performed.
    § 53.023. Payment Secured by Lien


    The lien secures payment for:

    (1) the labor done or material furnished for the construction or
    repair;

    (2) the specially fabricated material, even if the material has not
    been delivered or incorporated into the construction or repair, less
    its fair salvage value; or

    (3) the preparation of a plan or plat by an architect, engineer, or
    surveyor in accordance with Section 53.021(c).
    § 53.024. Limitation on Subcontractor's Lien


    The amount of a lien claimed by a subcontractor may not exceed:

    (1) an amount equal to the proportion of the total subcontract price
    that the sum of the labor performed, materials furnished, materials
    specially fabricated, reasonable overhead costs incurred, and
    proportionate profit margin bears to the total subcontract price;
    minus

    (2) the sum of previous payments received by the claimant on the
    subcontract.
    § 53.025. Limitation on Ordinary Retainage Lien


    A lien for retainage is valid only for the amount specified to be
    retained in the contract, including any amendments to the contract,
    between the claimant and the original contractor or between the
    claimant and a subcontractor.
    § 53.026. Sham Contract


    (a) A person who labors, specially fabricates materials, or
    furnishes labor or materials under a direct contractual relationship
    with another person is considered to be in direct contractual
    relationship with the owner and has a lien as an original
    contractor, if:

    (1) the owner contracted with the other person for the construction
    or repair of a house, building, or improvements and the owner can
    effectively control that person through ownership of voting stock,
    interlocking directorships, or otherwise;

    (2) the owner contracted with the other person for the construction
    or repair of a house, building, or improvements and that other
    person can effectively control the owner through ownership of voting
    stock, interlocking directorships, or otherwise; or

    (3) the owner contracted with the other person for the construction
    or repair of a house, building, or improvements and the contract was
    made without good faith intention of the parties that the other
    person was to perform the contract.

    (b) In this section, "owner" does not include a person who has or
    claims a security interest only.
    [Sections 53.027 to 53.050 reserved for expansion]


    SUBCHAPTER C PROCEDURE FOR PERFECTING LIEN

    § 53.051. Necessary Procedures


    To perfect the lien, a person must comply with this subchapter.
    § 53.052. Filing of Affidavit


    (a) Except as provided by Subsection (b), the person claiming the
    lien must file an affidavit with the county clerk of the county in
    which the property is located or into which the railroad extends not
    later than the 15th day of the fourth calendar month after the day
    on which the indebtedness accrues.

    (b) A person claiming a lien arising from a residential construction
    project must file an affidavit with the county clerk of the county
    in which the property is located not later than the 15th day of the
    third calendar month after the day on which the indebtedness
    accrues.

    (c) The county clerk shall record the affidavit in records kept for
    that purpose and shall index and cross-index the affidavit in the
    names of the claimant, the original contractor, and the owner.
    Failure of the county clerk to properly record or index a filed
    affidavit does not invalidate the lien.
    § 53.053. Accrual of Indebtedness


    (a) For purposes of Section 53.052, indebtedness accrues on a
    contract under which a plan or plat is prepared, labor was
    performed, materials furnished, or specially fabricated materials
    are to be furnished in accordance with this section.

    (b) Indebtedness to an original contractor accrues:

    (1) on the last day of the month in which a written declaration by
    the original contractor or the owner is received by the other party
    to the original contract stating that the original contract has been
    terminated; or

    (2) on the last day of the month in which the original contract has
    been completed, finally settled, or abandoned.

    (c) Indebtedness to a subcontractor, or to any person not covered by
    Subsection (b) or (d), who has furnished labor or material to an
    original contractor or to another subcontractor accrues on the last
    day of the last month in which the labor was performed or the
    material furnished.

    (d) Indebtedness for specially fabricated material accrues:

    (1) on the last day of the last month in which materials were
    delivered;

    (2) on the last day of the last month in which delivery of the last
    of the material would normally have been required at the job site;
    or

    (3) on the last day of the month of any material breach or
    termination of the original contract by the owner or contractor or
    of the subcontract under which the specially fabricated material was
    furnished.

    (e) A claim for retainage accrues on the last day of the month in
    which all work called for by the contract between the owner and the
    original contractor has been completed, finally settled, or
    abandoned.
    § 53.054. Contents of Affidavit


    (a) The affidavit must be signed by the person claiming the lien or
    by another person on the claimant's behalf and must contain
    substantially:

    (1) a sworn statement of the amount of the claim;

    (2) the name and last known address of the owner or reputed owner;

    (3) a general statement of the kind of work done and materials
    furnished by the claimant and, for a claimant other than an original
    contractor, a statement of each month in which the work was done and
    materials furnished for which payment is requested;

    (4) the name and last known address of the person by whom the
    claimant was employed or to whom the claimant furnished the
    materials or labor;

    (5) the name and last known address of the original contractor;

    (6) a description, legally sufficient for identification, of the
    property sought to be charged with the lien;

    (7) the claimant's name, mailing address, and, if different,
    physical address; and

    (8) for a claimant other than an original contractor, a statement
    identifying the date each notice of the claim was sent to the owner
    and the method by which the notice was sent.

    (b) The claimant may attach to the affidavit a copy of any
    applicable written agreement or contract and a copy of each notice
    sent to the owner.

    (c) The affidavit is not required to set forth individual items of
    work done or material furnished or specially fabricated.

    The affidavit may use any abbreviations or symbols customary in the
    trade.
    § 53.055. Notice of Filed Affidavit


    (a) A person who files an affidavit must send a copy of the
    affidavit by registered or certified mail to the owner or reputed
    owner at the owner's last known business or residence address not
    later than the fifth day after the date the affidavit is filed with
    the county clerk.

    (b) If the person is not an original contractor, the person must
    also send a copy of the affidavit to the original contractor at the
    original contractor's last known business or residence address
    within the same period.
    § 53.056. Derivative Claimant: Notice to Owner or Original
    Contractor


    (a) Except as provided by Subchapter K, [FN1] a claimant other than
    an original contractor must give the notice prescribed by this
    section for the lien to be valid.

    (b) If the lien claim arises from a debt incurred by a
    subcontractor, the claimant must give to the original contractor
    written notice of the unpaid balance. The claimant must give the
    notice not later than the 15th day of the second month following
    each month in which all or part of the claimant's labor was
    performed or material delivered. The claimant must give the same
    notice to the owner or reputed owner and the original contractor not
    later than the 15th day of the third month following each month in
    which all or part of the claimant's labor was performed or material
    or specially fabricated material was delivered.

    (c) If the lien claim arises from a debt incurred by the original
    contractor, the claimant must give notice to the owner or reputed
    owner, with a copy to the original contractor, in accordance with
    Subsection (b).

    (d) To authorize the owner to withhold funds under Subchapter D,
    [FN2] the notice to the owner must state that if the claim remains
    unpaid, the owner may be personally liable and the owner's property
    may be subjected to a lien unless:

    (1) the owner withholds payments from the contractor for payment of
    the claim; or

    (2) the claim is otherwise paid or settled.

    (e) The notice must be sent by registered or certified mail and must
    be addressed to the owner or reputed owner or the original
    contractor, as applicable, at his last known business or residence
    address.

    (f) A copy of the statement or billing in the usual and customary
    form is sufficient as notice under this section.
    § 53.057. Derivative Claimant: Notice for Contractual Retainage
    Claim


    (a) A claimant may give notice under this section instead of or in
    addition to notice under Section 53.056 or 53.252 if the claimant is
    to labor, furnish labor or materials, or specially fabricate
    materials under an agreement with an original contractor or a
    subcontractor providing for retainage.

    (b) The claimant must give the owner or reputed owner notice of the
    retainage agreement not later than the 15th day of the second month
    following the delivery of materials or the performance of labor by
    the claimant that first occurs after the claimant has agreed to the
    contractual retainage. If the agreement is with a subcontractor, the
    claimant must also give notice within that time to the original
    contractor.

    (c) The notice must contain:

    (1) the sum to be retained;

    (2) the due date or dates, if known; and

    (3) a general indication of the nature of the agreement.

    (d) The notice must be sent by registered or certified mail to the
    last known business or residence address of the owner or reputed
    owner or the original contractor, as applicable.

    (e) If a claimant gives notice under this section and Section 53.055
    or, if the claim relates to a residential construction project,
    under this section and Section 53.252, the claimant is not required
    to give any other notice as to the retainage.
    § 53.058. Derivative Claimant: Notice for Specially Fabricated Items


    (a) Except as provided by Subchapter K, [FN1] a claimant who
    specially fabricates material must give notice under this section
    for the lien to be valid.

    (b) The claimant must give the owner or reputed owner notice not
    later than the 15th day of the second month after the month in which
    the claimant receives and accepts the order for the material. If the
    indebtedness is incurred by a person other than the original
    contractor, the claimant must also give notice within that time to
    the original contractor.

    (c) The notice must contain:

    (1) a statement that the order has been received and accepted; and

    (2) the price of the order.

    (d) The notice must be sent by registered or certified mail to the
    last known business or residence address of the owner or the reputed
    owner or the original contractor, as applicable.
    (e) In addition to notice under this section, the claimant must give
    notice under Section 53.056 if delivery has been made or if the
    normal delivery time for the job has passed.


    (f) The lien of a claimant who accepts an order but fails to give
    notice under this section is valid as to delivered items if the
    claimant has given notice under Section 53.056.

    (g) If a retainage agreement consists in whole or part of an
    obligation to furnish specially fabricated materials and the
    claimant has given notice under Section 53.057, the claimant is not
    required to give notice under this section.
    § 53.059. Repealed by Acts 1997, 75th Leg., ch. 526, § 24, eff.
    Sept. 1, 1997

    [Sections 53.060 to 53.080 reserved for expansion]

    SUBCHAPTER D FUNDS WITHHELD BY OWNER FOLLOWING NOTICE

    § 53.081. Authority to Withhold Funds for Benefit of Claimants


    (a) If an owner receives notice under Section 53.056, 53.057,
    53.058, 53.252, or 53.253, the owner may withhold from payments to
    the original contractor an amount necessary to pay the claim for
    which he receives notice.

    (b) If notice is sent in a form that substantially complies with
    Section 53.056 or 53.252, the owner may withhold the funds
    immediately on receipt of the notice.

    (c) If notice is sent under Section 53.057, the owner may withhold
    funds immediately on receipt of a copy of the claimant's affidavit
    prepared in accordance with Sections 53.052 through 53.055.

    (d) If notice is sent under Section 53.058, the owner may withhold
    funds immediately on receipt of the notices sent under Subsection
    (e) of that section. If notice is sent as provided by Section 53.253
    (b), the owner may withhold funds immediately on receipt of the
    notice sent as required by Section 53.252.
    § 53.082. Time for Which Funds are Withheld


    Unless payment is made under Section 53.083 or the claim is
    otherwise settled, discharged, indemnified against under Subchapter
    H or I, [FN1] or determined to be invalid by a final judgment of a
    court, the owner shall retain the funds withheld until:

    (1) the time for filing the affidavit of mechanic's lien has passed;
    or

    (2) if a lien affidavit has been filed, until the lien claim has
    been satisfied or released.
    § 53.083. Payment to Claimant on Demand


    (a) The claimant may make written demand for payment of the claim to
    an owner authorized to withhold funds under this subchapter. The
    demand must give notice to the owner that all or part of the claim
    has accrued under Section 53.053 or is past due according to the
    agreement between the parties.

    (b) The claimant must send a copy of the demand to the original
    contractor. The original contractor may give the owner written
    notice that the contractor intends to dispute the claim. The
    original contractor must give the notice not later than the 30th day
    after the day he receives the copy of the demand. If the original
    contractor does not give the owner timely notice, he is considered
    to have assented to the demand and the owner shall pay the claim.

    (c) The claimant's demand may accompany the original notice of
    nonpayment or of a past-due claim and may be stamped or written in
    legible form on the face of the notice.

    (d) Unless the lien has been secured, the demand may not be made
    after expiration of the time within which the claimant may secure
    the lien for the claim.
    § 53.084. Owner's Liability


    (a) Except for the amount required to be retained under Subchapter
    E, [FN1] the owner is not liable for any amount paid to the original
    contractor before the owner is authorized to withhold funds under
    this subchapter.

    (b) If the owner has received the notices required by Subchapter C
    [FN2] or K, [FN3] if the lien has been secured, and if the claim has
    been reduced to final judgment, the owner is liable and the owner's
    property is subject to a claim for any money paid to the original
    contractor after the owner was authorized to withhold funds under
    this subchapter. The owner is liable for that amount in addition to
    any amount for which he is liable under Subchapter E.
    § 53.085. Affidavit Required


    (a) Any person who furnishes labor or materials for the construction
    of improvements on real property shall, if requested and as a
    condition of payment for such labor or materials, provide to the
    requesting party, or the party's agent, an affidavit stating that
    the person has paid each of the person's subcontractors, laborers,
    or materialmen in full for all labor and materials provided to the
    person for the construction. In the event, however, that the person
    has not paid each of the person's subcontractors, laborers, or
    materialmen in full, the person shall state in the affidavit the
    amount owed and the name and, if known, the address and telephone
    number of each subcontractor, laborer, or materialman to whom the
    payment is owed.

    (b) The seller of any real property shall, upon request by the
    purchaser or the purchaser's agent prior to closing of the purchase
    of the real property, provide to the purchaser or the purchaser's
    agent, a written affidavit stating that the seller has paid each of
    the seller's contractors, laborers, or materialmen in full for all
    labor and materials provided to the seller through the date
    specified in the affidavit for any construction of improvements on
    the real property and that the seller is not indebted to any person,
    firm, or corporation by reason of any such construction through the
    date specified in the affidavit. In the event that the seller has
    not paid each of the seller's contractors, laborers, or materialmen
    in full for labor and material provided through the date specified
    in the affidavit, the seller shall state in the affidavit the amount
    owed and the name and, if known, the address and telephone number of
    each contractor, laborer, or materialman to whom the payment is
    owed.

    (c) The affidavit may include:

    (1) a waiver or release of lien rights by the affiant that is
    conditioned on the receipt of actual payment or collection of funds
    when payment is made by check or draft;

    (2) a warranty or representation that certain bills or classes of
    bills will be paid by the affiant from funds paid in reliance on the
    affidavit; and

    (3) an indemnification by the affiant for any loss or expense
    resulting from false or incorrect information in the affidavit.

    (d) A person, including a seller, commits an offense if the person
    intentionally, knowingly, or recklessly makes a false or misleading
    statement in an affidavit under this section. An offense under this
    section is a misdemeanor. A person adjudged guilty of an offense
    under this section shall be punished by a fine not to exceed $4,000
    or confinement in jail for a term not to exceed one year or both a
    fine and confinement. A person may not receive community supervision
    for the offense.

    (e) A person signing an affidavit under this section is personally
    liable for any loss or damage resulting from any false or incorrect
    information in the affidavit.
    [Sections 53.086 to 53.100 reserved for expansion]

    SUBCHAPTER E REQUIRED RETAINAGE FOR BENEFIT OF LIEN CLAIMANTS

    § 53.101. Required Retainage


    (a) During the progress of work under an original contract for which
    a mechanic's lien may be claimed and for 30 days after the work is
    completed, the owner shall retain:

    (1) 10 percent of the contract price of the work to the owner; or

    (2) 10 percent of the value of the work, measured by the proportion
    that the work done bears to the work to be done, using the contract
    price or, if there is no contract price, using the reasonable value
    of the completed work.

    (b) In this section, "owner" includes the owner's agent, trustee, or
    receiver.
    § 53.102. Payment Secured by Retainage


    The retained funds secure the payment of artisans and mechanics who
    perform labor or service and the payment of other persons who
    furnish material, material and labor, or specially fabricated
    material for any contractor, subcontractor, agent, or receiver in
    the performance of the work.
    § 53.103. Lien on Retained Funds


    A claimant has a lien on the retained funds if the claimant:

    (1) sends the notices required by this chapter in the time and
    manner required; and

    (2) files an affidavit claiming a lien not later than the 30th day
    after the work is completed.
    § 53.104. Preferences


    (a) Individual artisans and mechanics are entitled to a preference
    to the retained funds and shall share proportionately to the extent
    of their claims for wages and fringe benefits earned.

    (b) After payment of artisans and mechanics who are entitled to a
    preference under Subsection (a), other participating claimants share
    proportionately in the balance of the retained funds.
    § 53.105. Owner's Liability for Failure to Retain


    (a) If the owner fails or refuses to comply with this subchapter,
    the claimants complying with this chapter have a lien, at least to
    the extent of the amount that should have been retained from the
    original contract under which they are claiming, against the house,
    building, structure, fixture, or improvement and all of its
    properties and against the lot or lots of land necessarily
    connected.

    (b) The claimants share the lien proportionately in accordance with
    the preference provided by Section 53.104.
    § 53.106. Affidavit of Completion


    (a) An owner may file with the county clerk of the county in which
    the property is located an affidavit of completion. The affidavit
    must contain:

    (1) the name and address of the owner;

    (2) the name and address of the original contractor;

    (3) a description, legally sufficient for identification, of the
    real property on which the improvements are located;

    (4) a description of the improvements furnished under the original
    contract;

    (5) a statement that the improvements under the original contract
    have been completed and the date of completion; and

    (6) a conspicuous statement that a claimant may not have a lien on
    retained funds unless the claimant files the affidavit claiming a
    lien not later than the 30th day after the date of completion.

    (b) A copy of the affidavit must be sent by certified or registered
    mail to the original contractor not later than the date the
    affidavit is filed and to each claimant who sends a notice of lien
    liability to the owner under Section 53.056, 53.057, 53.058, 53.252,
    or 53.253 not later than the date the affidavit is filed or the 10th
    day after the date the owner receives the notice of lien liability,
    whichever is later.

    (c) A copy of the affidavit must also be sent to each person who
    furnishes labor or materials for the property and who furnishes the
    owner with a written request for the copy. The owner must furnish
    the copy to the person not later than the date the affidavit is
    filed or the 10th day after the date the request is received,
    whichever is later.

    (d) Except as provided by this subsection, an affidavit filed under
    this section on or before the 10th day after the date of completion
    of the improvements is prima facie evidence of the date the work
    under the original contract is completed for purposes of this
    subchapter. If the affidavit is filed after the 10th day after the
    date of completion, the date of completion for purposes of this
    subchapter is the date the affidavit is filed. This subsection does
    not apply to a person to whom the affidavit was not sent as required
    by this section.

    (e) Repealed by Acts 1999, 76th Leg., ch. 889, § 12, eff. Sept. 1,
    1999.
    [Sections 53.107 to 53.120 reserved for expansion]

    SUBCHAPTER F PRIORITIES AND PREFERENCES

    § 53.121. Preference Over Other Creditors


    All subcontractors, laborers, and materialmen who have a mechanic's
    lien have preference over other creditors of the original
    contractor.
    § 53.122. Equality of Mechanic's Liens


    (a) Except as provided by Subchapter E [FN1] and Section 53.124(e),
    perfected mechanic's liens are on equal footing without reference to
    the date of filing the affidavit claiming the lien.

    (b) If the proceeds of a foreclosure sale of property are
    insufficient to discharge all mechanic's liens against the property,
    the proceeds shall be paid pro rata on the perfected mechanic's
    liens on which suit is brought.

    (c) This chapter does not affect the contract between the owner and
    the original contractor as to the amount, manner, or time of payment
    of the contract price.
    § 53.123. Priority of Mechanic's Lien Over Other Liens


    (a) Except as provided by this section, a mechanic's lien attaches
    to the house, building, improvements, or railroad property in
    preference to any prior lien, encumbrance, or mortgage on the land
    on which it is located, and the person enforcing the lien may have
    the house, building, improvement, or any piece of the railroad
    property sold separately.

    (b) The mechanic's lien does not affect any lien, encumbrance, or
    mortgage on the land or improvement at the time of the inception of
    the mechanic's lien, and the holder of the lien, encumbrance, or
    mortgage need not be made a party to a suit to foreclose the
    mechanic's lien.
    § 53.124. Inception of Mechanic's Lien


    (a) Except as provided by Subsection (e), for purposes of Section
    53.123, the time of inception of a mechanic's lien is the
    commencement of construction of improvements or delivery of
    materials to the land on which the improvements are to be located
    and on which the materials are to be used.

    (b) The construction or materials under Subsection (a) must be
    visible from inspection of the land on which the improvements are
    being made.

    (c) An owner and original contractor may jointly file an affidavit
    of commencement with the county clerk of the county in which the
    land is located not later than the 30th day after the date of actual
    commencement of construction of the improvements or delivery of
    materials to the land. The affidavit must contain:

    (1) the name and address of the owner;

    (2) the name and address of each original contractor, known at the
    time to the owner, that is furnishing labor, service, or materials
    for the construction of the improvements;

    (3) a description, legally sufficient for identification, of the
    property being improved;

    (4) the date the work actually commenced; and

    (5) a general description of the improvement.

    (d) An affidavit filed in compliance with this section is prima
    facie evidence of the date of the commencement of the improvement
    described in the affidavit. The time of inception of a mechanic's
    lien arising from work described in an affidavit of commencement is
    the date of commencement of the work stated in the affidavit.

    (e) The time of inception of a lien that is created under Section
    53.021(c) or (d) is the date of recording of an affidavit of lien
    under Section 53.052. The priority of a lien claimed by a person
    entitled to a lien under Section 53.021(c) or (d) with respect to
    other mechanic's liens is determined by the date of recording. A
    lien created under Section 53.021(c) or (d) is not valid or
    enforceable against a grantee or purchaser who acquires an interest
    in the real property before the time of inception of the lien.
    [Sections 53.125 to 53.150 reserved for expansion]

    SUBCHAPTER G RELEASE AND FORECLOSURE; ACTION ON CLAIM TEXAS PROPERTY

    § 53.151. Enforcement of Remedies Against Money Due Original
    Contractor or Subcontractor


    (a) A creditor of an original contractor may not collect, enforce a
    security interest against, garnish, or levy execution on the money
    due the original contractor or the contractor's surety from the
    owner, and a creditor of a subcontractor may not collect, enforce a
    security interest against, garnish, or levy execution on the money
    due the subcontractor, to the prejudice of the subcontractors,
    mechanics, laborers, materialmen, or their sureties.

    (b) A surety issuing a payment bond or performance bond in
    connection with the improvements has a priority claim over other
    creditors of its principal to contract funds to the extent of any
    loss it suffers or incurs. That priority does not excuse the surety
    from paying any obligations that it may have under its payment
    bonds.
    § 53.152. Release of Claim or Lien


    (a) When a debt for labor or materials is satisfied or paid by
    collected funds, the person who furnished the labor or materials
    shall, not later than the 10th day after the date of receipt of a
    written request, furnish to the requesting person a release of the
    indebtedness and any lien claimed, to the extent of the indebtedness
    paid. An owner, the original contractor, or any person making the
    payment may request the release.

    (b) A release of lien must be in a form that would permit it to be
    filed of record.
    § 53.153. Defense of Actions


    (a) If an affidavit claiming a mechanic's lien is filed by a person
    other than the original contractor, the original contractor shall
    defend at his own expense a suit brought on the claim.

    (b) If the suit results in judgment on the lien against the owner or
    the owner's property, the owner is entitled to deduct the amount of
    the judgment and costs from any amount due the original contractor.
    If the owner has settled with the original contractor in full, the
    owner is entitled to recover from the original contractor any amount
    paid for which the original contractor was originally liable.
    § 53.154. Foreclosure


    A mechanic's lien may be foreclosed only on judgment of a court of
    competent jurisdiction foreclosing the lien and ordering the sale of
    the property subject to the lien.
    § 53.155. Transfer of Property Sold


    If the house, building, improvement, or any piece of railroad
    property is sold separately, the officer making the sale shall place
    the purchaser in possession. The purchaser is entitled to a
    reasonable time after the date of purchase within which to remove
    the purchased property.
    § 53.156. Costs and Attorney's Fees


    In any proceeding to foreclose a lien or to enforce a claim against
    a bond issued under Subchapter H, I, or J [FN1] or in any proceeding
    to declare that any lien or claim is invalid or unenforceable in
    whole or in part, the court may award costs and reasonable
    attorney's fees as are equitable and just.
    § 53.157. Discharge of Lien


    A mechanic's lien or affidavit claiming a mechanic's lien filed
    under Section 53.052 may be discharged of record by:

    (1) recording a lien release signed by the claimant under Section
    53.152;

    (2) failing to institute suit to foreclose the lien in the county in
    which the property is located within the period prescribed by
    Section 53.158, 53.175, or 53.208;

    (3) recording the original or certified copy of a final judgment or
    decree of a court of competent jurisdiction providing for the
    discharge;

    (4) filing the bond and notice in compliance with Subchapter H;
    [FN1]

    (5) filing the bond in compliance with Subchapter I; [FN2] or

    § 53.158. Period for Bringing Suit to Foreclose Lien

    (a) Except as provided by Subsection (b), suit must be brought to
    foreclose the lien within two years after the last day a claimant
    may file the lien affidavit under Section 53.052 or within one year
    after completion, termination, or abandonment of the work under the
    original contract under which the lien is claimed, whichever is
    later.

    (b) For a claim arising from a residential construction project,
    suit must be brought to foreclose the lien within one year after the
    last day a claimant may file a lien affidavit under Section 53.052
    or within one year after completion, termination, or abandonment of
    the work under the original contract under which the lien is
    claimed, whichever is later.


    On 3/15/05, v wrote:
    > Have you checked the revised
    > codes? Joisey is two years. Used to
    > be 20. With the option to renew the
    > lien in the twenyfirst year. Then
    > it ran till paid.
    >
    >
    > On 3/15/05, roosta wrote:
    >> On 3/15/05, Curmudgeon wrote:
    >>> Perhaps someone can pitch in if
    > there is some peculiarity in
    >>> Texas law. The general rule is
    > that mechanics liens expire
    >>> after one year if they are not
    > foreclosed. In other words,
    >>> you can't just sit on it. You
    > either foreclose or lose the
    >>> lien.
    >>
    > http://www.capitol.state.tx.us/statu
    > tes/pr.toc.htm
    >> PROPERTY CODE
    >> Title 5
    >> CHAPTER 53. MECHANIC'S,
    > CONTRACTOR'S, OR MATERIALMAN'S LIEN

    Posts on this thread, including this one
  • machenics lein / texas, 3/15/05, by debi zerby.
  • Re: machenics lein / texas, 3/15/05, by roosta.
  • Re: machenics lein / texas, 3/15/05, by Curmudgeon.
  • Re: machenics lein / texas, 3/15/05, by roosta.
  • Re: machenics lein / texas Roo, 3/15/05, by v.
  • Re: machenics lein / texas Roo, 3/15/05, by Curmudgeon.
  • Re: machenics lein / texas Roo, 3/15/05, by Curmudgeon---Don't Open My Last Post.
  • Re: machenics lein / Time out for Mudge, 3/15/05, by v.
  • Re: machenics lein last post, 3/15/05, by roosta.
  • Re: machenics lein last post Roo, 3/15/05, by v.
  • Re: machenics lein last post Roo, 3/16/05, by Michael.
  • Re: machenics lein last post Mikey, 3/16/05, by roosta.
  • Re: machenics lein last post Roo, 3/16/05, by Michael.
  • Re: machenics lein last post Roo, 3/16/05, by v.
  • Re: machenics lein last post V, 3/17/05, by Michael.


  Site Map:  Home Chatboards Legal Jobs Classified Ads Search Contacts Advertise
  © 1996 - 2013. All Rights Reserved. Please review our Terms of Use, Mission Statement, and Privacy Policy.