Follow us!

    Re: machenics lein / Time out for Mudge

    Posted by v on 3/15/05

    On 3/15/05, Curmudgeon---Don't Open
    My Last Post wrote:
    > I don't know what happened.
    Tried to copy a single section, but
    the
    > whole damn chapter appeared.
    >
    Mudge! How many post it notes
    have you had today?


    > On 3/15/05, Curmudgeon wrote:
    >> TEXAS PROPERTY CODE
    >> [Mechanic's Lien Statutes in
    effect as of August 1, 2003]
    >> [Does not include any changes
    which may become effective at a
    later
    >> date]
    >>
    >> CHAPTER 53. MECHANIC'S,
    CONTRACTOR'S, OR MATERIALMAN'S LIEN
    >>
    >> TABLE OF CONTENTS
    >>
    >> SUBCHAPTER A. GENERAL PROVISIONS
    >>
    >>
    >> § 53.001. Definitions
    >>
    >> § 53.002. More Than One Original
    Contractor
    >>
    >> § 53.003. Notices"
    >>
    >> § 53.004. reserved for expansion
    >>
    >> § 53.020. reserved for expansion
    >> SUBCHAPTER B PERSONS ENTITLED TO
    LIEN; SUBJECT PROPERTY
    >>
    >>
    >> § 53.021. Persons Entitled to
    Lien
    >>
    >> § 53.022. Property to Which Lien
    Extends
    >>
    >> § 53.023. Payment Secured by
    Lien
    >>
    >> § 53.024. Limitation on
    Subcontractor's Lien
    >>
    >> § 53.025. Limitation on Ordinary
    Retainage Lien
    >>
    >> § 53.026. Sham Contract
    >>
    >> § 53.027. reserved for expansion
    >>
    >> § 53.028. reserved for expansion
    >> SUBCHAPTER C PROCEDURE FOR
    PERFECTING LIEN
    >>
    >>
    >> § 53.051. Necessary Procedures
    >>
    >> § 53.052. Filing of Affidavit
    >>
    >> § 53.053. Accrual of
    Indebtedness
    >>
    >> § 53.054. Contents of Affidavit
    >>
    >> § 53.055. Notice of Filed
    Affidavit
    >>
    >> § 53.056. Derivative Claimant:
    Notice to Owner or Original
    >> Contractor
    >>
    >> § 53.057. Derivative Claimant:
    Notice for Contractual Retainage
    >> Claim
    >>
    >> § 53.058. Derivative Claimant:
    Notice for Specially Fabricated
    Items
    >>
    >> § 53.059. Repealed by Acts 1997,
    75th Leg., ch. 526, s 24, eff.
    >> Sept. 1, 1997
    >>
    >> § 53.060. reserved for expansion
    >>
    >> § 53.080. reserved for expansion
    >> SUBCHAPTER D FUNDS WITHHELD BY
    OWNER FOLLOWING NOTICE
    >>
    >>
    >> § 53.081. Authority to Withhold
    Funds for Benefit of Claimants
    >>
    >> § 53.082. Time for Which Funds
    are Withheld
    >>
    >> § 53.083. Payment to Claimant on
    Demand
    >>
    >> § 53.084. Owner's Liability
    >>
    >> § 53.085. Affidavit Required
    >>
    >> § 53.086. reserved for expansion
    >>
    >> § 53.100. reserved for expansion
    >> SUBCHAPTER E REQUIRED RETAINAGE
    FOR BENEFIT OF LIEN CLAIMANTS
    >>
    >>
    >> § 53.101. Required Retainage
    >>
    >> § 53.102. Payment Secured by
    Retainage
    >>
    >> § 53.103. Lien on Retained Funds
    >>
    >> § 53.104. Preferences
    >>
    >> § 53.105. Owner's Liability for
    Failure to Retain
    >>
    >> § 53.106. Affidavit of
    Completion
    >>
    >> § 53.107. reserved for expansion
    >>
    >> § 53.120. reserved for expansion
    >> SUBCHAPTER F PRIORITIES AND
    PREFERENCES
    >>
    >>
    >> § 53.121. Preference Over Other
    Creditors
    >>
    >> § 53.122. Equality of Mechanic's
    Liens
    >>
    >> § 53.123. Priority of Mechanic's
    Lien Over Other Liens
    >>
    >> § 53.124. Inception of
    Mechanic's Lien
    >>
    >> § 53.125. reserved for expansion
    >>
    >> § 53.150. reserved for expansion
    >> SUBCHAPTER G RELEASE AND
    FORECLOSURE; ACTION ON CLAIM
    >>
    >>
    >> § 53.151. Enforcement of
    Remedies Against Money Due Original
    >> Contractor
    >>
    >> or Subcontractor
    >>
    >> § 53.152. Release of Claim or
    Lien
    >>
    >> § 53.153. Defense of Actions
    >>
    >> § 53.154. Foreclosure
    >>
    >> § 53.155. Transfer of Property
    Sold
    >>
    >> § 53.156. Costs and Attorney's
    Fees
    >>
    >> § 53.157. Discharge of Lien
    >>
    >> § 53.158. Period for Bringing
    Suit to Foreclose Lien
    >>
    >> § 53.159. Obligation to Furnish
    Information
    >>
    >> § 53.160. Summary Motion to
    Remove Invalid or Unenforceable
    Lien
    >>
    >> § 53.161. Bond Requirements
    After Order to Remove
    >>
    >> § 53.162. Revival of Removed
    Lien
    >>
    >> § 53.163. reserved for expansion
    >>
    >> § 53.170. reserved for expansion
    >> SUBCHAPTER H BOND TO INDEMNIFY
    AGAINST LIEN
    >>
    >>
    >> § 53.171. Bond
    >>
    >> § 53.172. Bond Requirements
    >>
    >> § 53.173. Notice of Bond
    >>
    >> § 53.174. Recording of Bond and
    Notice
    >>
    >> § 53.175. Action on Bond
    >>
    >> § 53.176. Repealed by Acts 1989,
    71st Leg., ch. 1138, s 39(2), eff.
    >> Sept. 1, 1989
    >>
    >> § 53.177. reserved for expansion
    >>
    >> § 53.200. reserved for expansion
    >> SUBCHAPTER I BOND TO PAY LIENS
    OR CLAIMS
    >>
    >>
    >> § 53.201. Bond
    >>
    >> § 53.202. Bond Requirements
    >>
    >> § 53.203. Recording of Bond and
    Contract
    >>
    >> § 53.204. Reliance on Record
    >>
    >> § 53.205. Enforceable Claims
    >>
    >> § 53.206. Perfection of Claim
    >>
    >> § 53.207. Owner's Notice of
    Claim to Surety
    >>
    >> § 53.208. Action on Bond
    >>
    >> § 53.209. Repealed by Acts 1989,
    71st Leg., ch. 1138, s 39(3), eff.
    >> Sept. 1, 1989
    >>
    >> § 53.210. Claims in Excess of
    Bond Amount
    >>
    >> § 53.211. Attempted Compliance
    >>
    >> § 53.212. reserved for expansion
    >>
    >> § 53.230. reserved for expansion
    >> SUBCHAPTER J LIEN ON MONEY DUE
    PUBLIC WORKS CONTRACTOR
    >>
    >>
    >> § 53.231. Lien
    >>
    >> § 53.232. To Whom Notice Given;
    Manner
    >>
    >> § 53.233. Contents of Notice
    >>
    >> § 53.234. Time for Notice
    >>
    >> § 53.235. Official to Retain
    Funds
    >>
    >> § 53.236. Bond for Release of
    Lien
    >>
    >> § 53.237. Bond Requirements
    >>
    >> § 53.238. Notice of Bond
    >>
    >> § 53.239. Action on Bond
    >>
    >> § 53.240. Repealed by Acts 1989,
    71st Leg., ch. 1138, s 39(4), eff.
    >> Sept. 1, 1989
    >> SUBCHAPTER K RESIDENTIAL
    CONSTRUCTION PROJECTS
    >>
    >>
    >> § 53.251. Procedures for
    Residential Construction Projects
    >>
    >> § 53.252. Derivative Claimant:
    Notice to Owner or Original
    >> Contractor
    >>
    >> § 53.253. Derivative Claimant:
    Notice for Specially Fabricated
    Items
    >>
    >> § 53.254. Homestead
    >>
    >> § 53.255. Disclosure Statement
    Required for Residential
    Construction
    >> Contract
    >>
    >> § 53.256. List of Subcontractors
    and Suppliers
    >>
    >> § 53.257. Provisions Related to
    Closing of Loan for Construction of
    >> Improvements
    >>
    >> § 53.258. Disbursements of Funds
    >>
    >> § 53.259. Final Bills-Paid
    Affidavit Required
    >>
    >> § 53.260. Conveyance to
    Contractor Not Required
    >>
    >> CHAPTER 53. MECHANIC'S,
    CONTRACTOR'S, OR MATERIALMAN'S LIEN
    >>
    >>
    >> SUBCHAPTER A. GENERAL PROVISIONS
    >>
    >> § 53.001. Definitions
    >>
    >> In this chapter:
    >>
    >>
    >> (1) "Contract price" means the
    cost to the owner for any part of
    >> construction or repair performed
    under an original contract.
    >>
    >> (2) "Improvement" includes:
    >>
    >> (A) abutting sidewalks and
    streets and utilities in or on
    those
    >> sidewalks and streets;
    >>
    >> (B) clearing, grubbing,
    draining, or fencing of land;
    >>
    >> (C) wells, cisterns, tanks,
    reservoirs, or artificial lakes or
    pools
    >> made for supplying or storing
    water;
    >>
    >> (D) pumps, siphons, and
    windmills or other machinery or
    apparatuses
    >> used for raising water for
    stock, domestic use, or irrigation;
    and
    >>
    >> (E) planting orchard trees,
    grubbing out orchards and replacing
    >> trees, and pruning of orchard
    trees.
    >>
    >> (3) "Labor" means labor used in
    the direct prosecution of the work.
    >>
    >> (4) "Material" means all or part
    of:
    >>
    >> (A) the material, machinery,
    fixtures, or tools incorporated
    into
    >> the work, consumed in the direct
    prosecution of the work, or ordered
    >> and delivered for incorporation
    or consumption;
    >>
    >> (B) rent at a reasonable rate
    and actual running repairs at a
    >> reasonable cost for construction
    equipment used or reasonably
    >> required and delivered for use
    in the direct prosecution of the
    work
    >> at the site of the construction
    or repair; or
    >>
    >> (C) power, water, fuel, and
    lubricants consumed or ordered and
    >> delivered for consumption in the
    direct prosecution of the work.
    >>
    >> (5) "Mechanic's lien" means the
    lien provided by this chapter.
    >>
    >> (6) "Original contract" means an
    agreement to which an owner is a
    >> party either directly or by
    implication of law.
    >>
    >> (7) "Original contractor" means
    a person contracting with an owner
    >> either directly or through the
    owner's agent.
    >>
    >> (8) "Residence" means a single-
    family house, duplex, triplex, or
    >> quadruplex or a unit in a
    multiunit structure used for
    residential
    >> purposes that is:
    >>
    >> (A) owned by one or more adult
    persons; and (B) used or intended
    to
    >> be used as a dwelling by one of
    the owners.
    >>
    >> (9) "Residential construction
    contract" means a contract between
    an
    >> owner and a contractor in which
    the contractor agrees to construct
    >> or repair the owner's residence,
    including improvements appurtenant
    >> to the residence.
    >>
    >> (10) "Residential construction
    project" means a project for the
    >> construction or repair of a new
    or existing residence, including
    >> improvements appurtenant to the
    residence, as provided by a
    >> residential construction
    contract.
    >>
    >> (11) "Retainage" means an amount
    representing part of a contract
    >> payment that is not required to
    be paid to the claimant within the
    >> month following the month in
    which labor is performed, material
    is
    >> furnished, or specially
    fabricated material is delivered.
    The term
    >> does not include retainage under
    Subchapter E. [FN1]
    >>
    >> (12) "Specially fabricated
    material" means material fabricated
    for
    >> use as a component of the
    construction or repair so as to be
    >> reasonably unsuitable for use
    elsewhere.
    >>
    >> (13) "Subcontractor" means a
    person who has furnished labor or
    >> materials to fulfill an
    obligation to an original
    contractor or to a
    >> subcontractor to perform all or
    part of the work required by an
    >> original contract.
    >>
    >> (14) "Work" means any part of
    construction or repair performed
    under
    >> an original contract.
    >>
    >> (15) "Completion" of an original
    contract means the actual
    >> completion of the work,
    including any extras or change
    orders
    >> reasonably required or
    contemplated under the original
    contract,
    >> other than warranty work or
    replacement or repair of the work
    >> performed under the contract.
    >> § 53.002. More Than One Original
    Contractor
    >>
    >> On any work there may be more
    than one original contractor for
    >> purposes of this chapter.
    >>
    >> § 53.003. Notices
    >>
    >>
    >> (a) This section applies to
    notices required by Subchapters B
    >> through G and K. [FN1]
    >>
    >> (b) Any notice or other written
    communication may be delivered in
    >> person to the party entitled to
    the notice or to that party's
    agent,
    >> regardless of the manner
    prescribed by law.
    >>
    >> (c) If notice is sent by
    registered or certified mail,
    deposit or
    >> mailing of the notice in the
    United States mail in the form
    required
    >> constitutes compliance with the
    notice requirement. This subsection
    >> does not apply if the law
    requires receipt of the notice by
    the
    >> person to whom it is directed.
    >>
    >> (d) If a written notice is
    received by the person entitled to
    >> receive it, the method by which
    the notice was delivered is
    >> immaterial.
    >> [Sections 53.004 to 53.020
    reserved for expansion]
    >>
    >> SUBCHAPTER B PERSONS ENTITLED TO
    LIEN; SUBJECT PROPERTY
    >>
    >> § 53.021. Persons Entitled to
    Lien
    >>
    >>
    >> (a) A person has a lien if:
    >>
    >> (1) the person labors, specially
    fabricates material, or furnishes
    >> labor or materials for
    construction or repair in this
    state of:
    >>
    >> (A) a house, building, or
    improvement;
    >>
    >> (B) a levee or embankment to be
    erected for the reclamation of
    >> overflow land along a river or
    creek; or
    >>
    >> (C) a railroad; and
    >>
    >> (2) the person labors, specially
    fabricates the material, or
    >> furnishes the labor or materials
    under or by virtue of a contract
    >> with the owner or the owner's
    agent, trustee, receiver,
    contractor,
    >> or subcontractor.
    >>
    >> (b) A person who specially
    fabricates material has a lien even
    if
    >> the material is not delivered.
    >>
    >> (c) An architect, engineer, or
    surveyor who prepares a plan or
    plat
    >> under or by virtue of a written
    contract with the owner or the
    >> owner's agent, trustee, or
    receiver in connection with the
    actual or
    >> proposed design, construction,
    or repair of improvements on real
    >> property or the location of the
    boundaries of real property has a
    >> lien on the property.
    >>
    >> (d) A person who provides labor,
    plant material, or other supplies
    >> for the installation of
    landscaping for a house, building,
    or
    >> improvement, including the
    construction of a retention pond,
    >> retaining wall, berm, irrigation
    system, fountain, or other similar
    >> installation, under or by virtue
    of a written contract with the
    >> owner or the owner's agent,
    trustee, or receiver has a lien on
    the
    >> property.
    >> § 53.022. Property to Which Lien
    Extends
    >>
    >>
    >> (a) The lien extends to the
    house, building, fixtures, or
    >> improvements, the land reclaimed
    from overflow, or the railroad and
    >> all of its properties, and to
    each lot of land necessarily
    connected
    >> or reclaimed.
    >>
    >> (b) The lien does not extend to
    abutting sidewalks, streets, and
    >> utilities that are public
    property.
    >>
    >> (c) A lien against land in a
    city, town, or village extends to
    each
    >> lot on which the house,
    building, or improvement is
    situated or on
    >> which the labor was performed.
    >>
    >> (d) A lien against land not in a
    city, town, or village extends to
    >> not more than 50 acres on which
    the house, building, or improvement
    >> is situated or on which the
    labor was performed.
    >> § 53.023. Payment Secured by
    Lien
    >>
    >>
    >> The lien secures payment for:
    >>
    >> (1) the labor done or material
    furnished for the construction or
    >> repair;
    >>
    >> (2) the specially fabricated
    material, even if the material has
    not
    >> been delivered or incorporated
    into the construction or repair,
    less
    >> its fair salvage value; or
    >>
    >> (3) the preparation of a plan or
    plat by an architect, engineer, or
    >> surveyor in accordance with
    Section 53.021(c).
    >> § 53.024. Limitation on
    Subcontractor's Lien
    >>
    >>
    >> The amount of a lien claimed by
    a subcontractor may not exceed:
    >>
    >> (1) an amount equal to the
    proportion of the total subcontract
    price
    >> that the sum of the labor
    performed, materials furnished,
    materials
    >> specially fabricated, reasonable
    overhead costs incurred, and
    >> proportionate profit margin
    bears to the total subcontract
    price;
    >> minus
    >>
    >> (2) the sum of previous payments
    received by the claimant on the
    >> subcontract.
    >> § 53.025. Limitation on Ordinary
    Retainage Lien
    >>
    >>
    >> A lien for retainage is valid
    only for the amount specified to be
    >> retained in the contract,
    including any amendments to the
    contract,
    >> between the claimant and the
    original contractor or between the
    >> claimant and a subcontractor.
    >> § 53.026. Sham Contract
    >>
    >>
    >> (a) A person who labors,
    specially fabricates materials, or
    >> furnishes labor or materials
    under a direct contractual
    relationship
    >> with another person is
    considered to be in direct
    contractual
    >> relationship with the owner and
    has a lien as an original
    >> contractor, if:
    >>
    >> (1) the owner contracted with
    the other person for the
    construction
    >> or repair of a house, building,
    or improvements and the owner can
    >> effectively control that person
    through ownership of voting stock,
    >> interlocking directorships, or
    otherwise;
    >>
    >> (2) the owner contracted with
    the other person for the
    construction
    >> or repair of a house, building,
    or improvements and that other
    >> person can effectively control
    the owner through ownership of
    voting
    >> stock, interlocking
    directorships, or otherwise; or
    >>
    >> (3) the owner contracted with
    the other person for the
    construction
    >> or repair of a house, building,
    or improvements and the contract
    was
    >> made without good faith
    intention of the parties that the
    other
    >> person was to perform the
    contract.
    >>
    >> (b) In this section, "owner"
    does not include a person who has
    or
    >> claims a security interest only.
    >> [Sections 53.027 to 53.050
    reserved for expansion]
    >>
    >>
    >> SUBCHAPTER C PROCEDURE FOR
    PERFECTING LIEN
    >>
    >> § 53.051. Necessary Procedures
    >>
    >>
    >> To perfect the lien, a person
    must comply with this subchapter.
    >> § 53.052. Filing of Affidavit
    >>
    >>
    >> (a) Except as provided by
    Subsection (b), the person claiming
    the
    >> lien must file an affidavit with
    the county clerk of the county in
    >> which the property is located or
    into which the railroad extends not
    >> later than the 15th day of the
    fourth calendar month after the day
    >> on which the indebtedness
    accrues.
    >>
    >> (b) A person claiming a lien
    arising from a residential
    construction
    >> project must file an affidavit
    with the county clerk of the county
    >> in which the property is located
    not later than the 15th day of the
    >> third calendar month after the
    day on which the indebtedness
    >> accrues.
    >>
    >> (c) The county clerk shall
    record the affidavit in records
    kept for
    >> that purpose and shall index and
    cross-index the affidavit in the
    >> names of the claimant, the
    original contractor, and the owner.
    >> Failure of the county clerk to
    properly record or index a filed
    >> affidavit does not invalidate
    the lien.
    >> § 53.053. Accrual of
    Indebtedness
    >>
    >>
    >> (a) For purposes of Section
    53.052, indebtedness accrues on a
    >> contract under which a plan or
    plat is prepared, labor was
    >> performed, materials furnished,
    or specially fabricated materials
    >> are to be furnished in
    accordance with this section.
    >>
    >> (b) Indebtedness to an original
    contractor accrues:
    >>
    >> (1) on the last day of the month
    in which a written declaration by
    >> the original contractor or the
    owner is received by the other
    party
    >> to the original contract stating
    that the original contract has been
    >> terminated; or
    >>
    >> (2) on the last day of the month
    in which the original contract has
    >> been completed, finally settled,
    or abandoned.
    >>
    >> (c) Indebtedness to a
    subcontractor, or to any person not
    covered by
    >> Subsection (b) or (d), who has
    furnished labor or material to an
    >> original contractor or to
    another subcontractor accrues on
    the last
    >> day of the last month in which
    the labor was performed or the
    >> material furnished.
    >>
    >> (d) Indebtedness for specially
    fabricated material accrues:
    >>
    >> (1) on the last day of the last
    month in which materials were
    >> delivered;
    >>
    >> (2) on the last day of the last
    month in which delivery of the last
    >> of the material would normally
    have been required at the job site;
    >> or
    >>
    >> (3) on the last day of the month
    of any material breach or
    >> termination of the original
    contract by the owner or contractor
    or
    >> of the subcontract under which
    the specially fabricated material
    was
    >> furnished.
    >>
    >> (e) A claim for retainage
    accrues on the last day of the
    month in
    >> which all work called for by the
    contract between the owner and the
    >> original contractor has been
    completed, finally settled, or
    >> abandoned.
    >> § 53.054. Contents of Affidavit
    >>
    >>
    >> (a) The affidavit must be signed
    by the person claiming the lien or
    >> by another person on the
    claimant's behalf and must contain
    >> substantially:
    >>
    >> (1) a sworn statement of the
    amount of the claim;
    >>
    >> (2) the name and last known
    address of the owner or reputed
    owner;
    >>
    >> (3) a general statement of the
    kind of work done and materials
    >> furnished by the claimant and,
    for a claimant other than an
    original
    >> contractor, a statement of each
    month in which the work was done
    and
    >> materials furnished for which
    payment is requested;
    >>
    >> (4) the name and last known
    address of the person by whom the
    >> claimant was employed or to whom
    the claimant furnished the
    >> materials or labor;
    >>
    >> (5) the name and last known
    address of the original contractor;
    >>
    >> (6) a description, legally
    sufficient for identification, of
    the
    >> property sought to be charged
    with the lien;
    >>
    >> (7) the claimant's name, mailing
    address, and, if different,
    >> physical address; and
    >>
    >> (8) for a claimant other than an
    original contractor, a statement
    >> identifying the date each notice
    of the claim was sent to the owner
    >> and the method by which the
    notice was sent.
    >>
    >> (b) The claimant may attach to
    the affidavit a copy of any
    >> applicable written agreement or
    contract and a copy of each notice
    >> sent to the owner.
    >>
    >> (c) The affidavit is not
    required to set forth individual
    items of
    >> work done or material furnished
    or specially fabricated.
    >>
    >> The affidavit may use any
    abbreviations or symbols customary
    in the
    >> trade.
    >> § 53.055. Notice of Filed
    Affidavit
    >>
    >>
    >> (a) A person who files an
    affidavit must send a copy of the
    >> affidavit by registered or
    certified mail to the owner or
    reputed
    >> owner at the owner's last known
    business or residence address not
    >> later than the fifth day after
    the date the affidavit is filed
    with
    >> the county clerk.
    >>
    >> (b) If the person is not an
    original contractor, the person
    must
    >> also send a copy of the
    affidavit to the original
    contractor at the
    >> original contractor's last known
    business or residence address
    >> within the same period.
    >> § 53.056. Derivative Claimant:
    Notice to Owner or Original
    >> Contractor
    >>
    >>
    >> (a) Except as provided by
    Subchapter K, [FN1] a claimant
    other than
    >> an original contractor must give
    the notice prescribed by this
    >> section for the lien to be
    valid.
    >>
    >> (b) If the lien claim arises
    from a debt incurred by a
    >> subcontractor, the claimant must
    give to the original contractor
    >> written notice of the unpaid
    balance. The claimant must give the
    >> notice not later than the 15th
    day of the second month following
    >> each month in which all or part
    of the claimant's labor was
    >> performed or material delivered.
    The claimant must give the same
    >> notice to the owner or reputed
    owner and the original contractor
    not
    >> later than the 15th day of the
    third month following each month in
    >> which all or part of the
    claimant's labor was performed or
    material
    >> or specially fabricated material
    was delivered.
    >>
    >> (c) If the lien claim arises
    from a debt incurred by the
    original
    >> contractor, the claimant must
    give notice to the owner or reputed
    >> owner, with a copy to the
    original contractor, in accordance
    with
    >> Subsection (b).
    >>
    >> (d) To authorize the owner to
    withhold funds under Subchapter D,
    >> [FN2] the notice to the owner
    must state that if the claim
    remains
    >> unpaid, the owner may be
    personally liable and the owner's
    property
    >> may be subjected to a lien
    unless:
    >>
    >> (1) the owner withholds payments
    from the contractor for payment of
    >> the claim; or
    >>
    >> (2) the claim is otherwise paid
    or settled.
    >>
    >> (e) The notice must be sent by
    registered or certified mail and
    must
    >> be addressed to the owner or
    reputed owner or the original
    >> contractor, as applicable, at
    his last known business or
    residence
    >> address.
    >>
    >> (f) A copy of the statement or
    billing in the usual and customary
    >> form is sufficient as notice
    under this section.
    >> § 53.057. Derivative Claimant:
    Notice for Contractual Retainage
    >> Claim
    >>
    >>
    >> (a) A claimant may give notice
    under this section instead of or in
    >> addition to notice under Section
    53.056 or 53.252 if the claimant is
    >> to labor, furnish labor or
    materials, or specially fabricate
    >> materials under an agreement
    with an original contractor or a
    >> subcontractor providing for
    retainage.
    >>
    >> (b) The claimant must give the
    owner or reputed owner notice of
    the
    >> retainage agreement not later
    than the 15th day of the second
    month
    >> following the delivery of
    materials or the performance of
    labor by
    >> the claimant that first occurs
    after the claimant has agreed to
    the
    >> contractual retainage. If the
    agreement is with a subcontractor,
    the
    >> claimant must also give notice
    within that time to the original
    >> contractor.
    >>
    >> (c) The notice must contain:
    >>
    >> (1) the sum to be retained;
    >>
    >> (2) the due date or dates, if
    known; and
    >>
    >> (3) a general indication of the
    nature of the agreement.
    >>
    >> (d) The notice must be sent by
    registered or certified mail to the
    >> last known business or residence
    address of the owner or reputed
    >> owner or the original
    contractor, as applicable.
    >>
    >> (e) If a claimant gives notice
    under this section and Section
    53.055
    >> or, if the claim relates to a
    residential construction project,
    >> under this section and Section
    53.252, the claimant is not
    required
    >> to give any other notice as to
    the retainage.
    >> § 53.058. Derivative Claimant:
    Notice for Specially Fabricated
    Items
    >>
    >>
    >> (a) Except as provided by
    Subchapter K, [FN1] a claimant who
    >> specially fabricates material
    must give notice under this section
    >> for the lien to be valid.
    >>
    >> (b) The claimant must give the
    owner or reputed owner notice not
    >> later than the 15th day of the
    second month after the month in
    which
    >> the claimant receives and
    accepts the order for the material.
    If the
    >> indebtedness is incurred by a
    person other than the original
    >> contractor, the claimant must
    also give notice within that time
    to
    >> the original contractor.
    >>
    >> (c) The notice must contain:
    >>
    >> (1) a statement that the order
    has been received and accepted; and
    >>
    >> (2) the price of the order.
    >>
    >> (d) The notice must be sent by
    registered or certified mail to the
    >> last known business or residence
    address of the owner or the reputed
    >> owner or the original
    contractor, as applicable.
    >> (e) In addition to notice under
    this section, the claimant must
    give
    >> notice under Section 53.056 if
    delivery has been made or if the
    >> normal delivery time for the job
    has passed.
    >>
    >>
    >> (f) The lien of a claimant who
    accepts an order but fails to give
    >> notice under this section is
    valid as to delivered items if the
    >> claimant has given notice under
    Section 53.056.
    >>
    >> (g) If a retainage agreement
    consists in whole or part of an
    >> obligation to furnish specially
    fabricated materials and the
    >> claimant has given notice under
    Section 53.057, the claimant is not
    >> required to give notice under
    this section.
    >> § 53.059. Repealed by Acts 1997,
    75th Leg., ch. 526, § 24, eff.
    >> Sept. 1, 1997
    >>
    >> [Sections 53.060 to 53.080
    reserved for expansion]
    >>
    >> SUBCHAPTER D FUNDS WITHHELD BY
    OWNER FOLLOWING NOTICE
    >>
    >> § 53.081. Authority to Withhold
    Funds for Benefit of Claimants
    >>
    >>
    >> (a) If an owner receives notice
    under Section 53.056, 53.057,
    >> 53.058, 53.252, or 53.253, the
    owner may withhold from payments to
    >> the original contractor an
    amount necessary to pay the claim
    for
    >> which he receives notice.
    >>
    >> (b) If notice is sent in a form
    that substantially complies with
    >> Section 53.056 or 53.252, the
    owner may withhold the funds
    >> immediately on receipt of the
    notice.
    >>
    >> (c) If notice is sent under
    Section 53.057, the owner may
    withhold
    >> funds immediately on receipt of
    a copy of the claimant's affidavit
    >> prepared in accordance with
    Sections 53.052 through 53.055.
    >>
    >> (d) If notice is sent under
    Section 53.058, the owner may
    withhold
    >> funds immediately on receipt of
    the notices sent under Subsection
    >> (e) of that section. If notice
    is sent as provided by Section
    53.253
    >> (b), the owner may withhold
    funds immediately on receipt of the
    >> notice sent as required by
    Section 53.252.
    >> § 53.082. Time for Which Funds
    are Withheld
    >>
    >>
    >> Unless payment is made under
    Section 53.083 or the claim is
    >> otherwise settled, discharged,
    indemnified against under
    Subchapter
    >> H or I, [FN1] or determined to
    be invalid by a final judgment of a
    >> court, the owner shall retain
    the funds withheld until:
    >>
    >> (1) the time for filing the
    affidavit of mechanic's lien has
    passed;
    >> or
    >>
    >> (2) if a lien affidavit has been
    filed, until the lien claim has
    >> been satisfied or released.
    >> § 53.083. Payment to Claimant on
    Demand
    >>
    >>
    >> (a) The claimant may make
    written demand for payment of the
    claim to
    >> an owner authorized to withhold
    funds under this subchapter. The
    >> demand must give notice to the
    owner that all or part of the claim
    >> has accrued under Section 53.053
    or is past due according to the
    >> agreement between the parties.
    >>
    >> (b) The claimant must send a
    copy of the demand to the original
    >> contractor. The original
    contractor may give the owner
    written
    >> notice that the contractor
    intends to dispute the claim. The
    >> original contractor must give
    the notice not later than the 30th
    day
    >> after the day he receives the
    copy of the demand. If the original
    >> contractor does not give the
    owner timely notice, he is
    considered
    >> to have assented to the demand
    and the owner shall pay the claim.
    >>
    >> (c) The claimant's demand may
    accompany the original notice of
    >> nonpayment or of a past-due
    claim and may be stamped or written
    in
    >> legible form on the face of the
    notice.
    >>
    >> (d) Unless the lien has been
    secured, the demand may not be made
    >> after expiration of the time
    within which the claimant may
    secure
    >> the lien for the claim.
    >> § 53.084. Owner's Liability
    >>
    >>
    >> (a) Except for the amount
    required to be retained under
    Subchapter
    >> E, [FN1] the owner is not liable
    for any amount paid to the original
    >> contractor before the owner is
    authorized to withhold funds under
    >> this subchapter.
    >>
    >> (b) If the owner has received
    the notices required by Subchapter
    C
    >> [FN2] or K, [FN3] if the lien
    has been secured, and if the claim
    has
    >> been reduced to final judgment,
    the owner is liable and the owner's
    >> property is subject to a claim
    for any money paid to the original
    >> contractor after the owner was
    authorized to withhold funds under
    >> this subchapter. The owner is
    liable for that amount in addition
    to
    >> any amount for which he is
    liable under Subchapter E.
    >> § 53.085. Affidavit Required
    >>
    >>
    >> (a) Any person who furnishes
    labor or materials for the
    construction
    >> of improvements on real property
    shall, if requested and as a
    >> condition of payment for such
    labor or materials, provide to the
    >> requesting party, or the party's
    agent, an affidavit stating that
    >> the person has paid each of the
    person's subcontractors, laborers,
    >> or materialmen in full for all
    labor and materials provided to the
    >> person for the construction. In
    the event, however, that the person
    >> has not paid each of the
    person's subcontractors, laborers,
    or
    >> materialmen in full, the person
    shall state in the affidavit the
    >> amount owed and the name and, if
    known, the address and telephone
    >> number of each subcontractor,
    laborer, or materialman to whom the
    >> payment is owed.
    >>
    >> (b) The seller of any real
    property shall, upon request by the
    >> purchaser or the purchaser's
    agent prior to closing of the
    purchase
    >> of the real property, provide to
    the purchaser or the purchaser's
    >> agent, a written affidavit
    stating that the seller has paid
    each of
    >> the seller's contractors,
    laborers, or materialmen in full
    for all
    >> labor and materials provided to
    the seller through the date
    >> specified in the affidavit for
    any construction of improvements on
    >> the real property and that the
    seller is not indebted to any
    person,
    >> firm, or corporation by reason
    of any such construction through
    the
    >> date specified in the affidavit.
    In the event that the seller has
    >> not paid each of the seller's
    contractors, laborers, or
    materialmen
    >> in full for labor and material
    provided through the date specified
    >> in the affidavit, the seller
    shall state in the affidavit the
    amount
    >> owed and the name and, if known,
    the address and telephone number of
    >> each contractor, laborer, or
    materialman to whom the payment is
    >> owed.
    >>
    >> (c) The affidavit may include:
    >>
    >> (1) a waiver or release of lien
    rights by the affiant that is
    >> conditioned on the receipt of
    actual payment or collection of
    funds
    >> when payment is made by check or
    draft;
    >>
    >> (2) a warranty or representation
    that certain bills or classes of
    >> bills will be paid by the
    affiant from funds paid in reliance
    on the
    >> affidavit; and
    >>
    >> (3) an indemnification by the
    affiant for any loss or expense
    >> resulting from false or
    incorrect information in the
    affidavit.
    >>
    >> (d) A person, including a
    seller, commits an offense if the
    person
    >> intentionally, knowingly, or
    recklessly makes a false or
    misleading
    >> statement in an affidavit under
    this section. An offense under this
    >> section is a misdemeanor. A
    person adjudged guilty of an
    offense
    >> under this section shall be
    punished by a fine not to exceed
    $4,000
    >> or confinement in jail for a
    term not to exceed one year or both
    a
    >> fine and confinement. A person
    may not receive community
    supervision
    >> for the offense.
    >>
    >> (e) A person signing an
    affidavit under this section is
    personally
    >> liable for any loss or damage
    resulting from any false or
    incorrect
    >> information in the affidavit.
    >> [Sections 53.086 to 53.100
    reserved for expansion]
    >>
    >> SUBCHAPTER E REQUIRED RETAINAGE
    FOR BENEFIT OF LIEN CLAIMANTS
    >>
    >> § 53.101. Required Retainage
    >>
    >>
    >> (a) During the progress of work
    under an original contract for
    which
    >> a mechanic's lien may be claimed
    and for 30 days after the work is
    >> completed, the owner shall
    retain:
    >>
    >> (1) 10 percent of the contract
    price of the work to the owner; or
    >>
    >> (2) 10 percent of the value of
    the work, measured by the
    proportion
    >> that the work done bears to the
    work to be done, using the contract
    >> price or, if there is no
    contract price, using the
    reasonable value
    >> of the completed work.
    >>
    >> (b) In this section, "owner"
    includes the owner's agent,
    trustee, or
    >> receiver.
    >> § 53.102. Payment Secured by
    Retainage
    >>
    >>
    >> The retained funds secure the
    payment of artisans and mechanics
    who
    >> perform labor or service and the
    payment of other persons who
    >> furnish material, material and
    labor, or specially fabricated
    >> material for any contractor,
    subcontractor, agent, or receiver
    in
    >> the performance of the work.
    >> § 53.103. Lien on Retained Funds
    >>
    >>
    >> A claimant has a lien on the
    retained funds if the claimant:
    >>
    >> (1) sends the notices required
    by this chapter in the time and
    >> manner required; and
    >>
    >> (2) files an affidavit claiming
    a lien not later than the 30th day
    >> after the work is completed.
    >> § 53.104. Preferences
    >>
    >>
    >> (a) Individual artisans and
    mechanics are entitled to a
    preference
    >> to the retained funds and shall
    share proportionately to the extent
    >> of their claims for wages and
    fringe benefits earned.
    >>
    >> (b) After payment of artisans
    and mechanics who are entitled to a
    >> preference under Subsection (a),
    other participating claimants share
    >> proportionately in the balance
    of the retained funds.
    >> § 53.105. Owner's Liability for
    Failure to Retain
    >>
    >>
    >> (a) If the owner fails or
    refuses to comply with this
    subchapter,
    >> the claimants complying with
    this chapter have a lien, at least
    to
    >> the extent of the amount that
    should have been retained from the
    >> original contract under which
    they are claiming, against the
    house,
    >> building, structure, fixture, or
    improvement and all of its
    >> properties and against the lot
    or lots of land necessarily
    >> connected.
    >>
    >> (b) The claimants share the lien
    proportionately in accordance with
    >> the preference provided by
    Section 53.104.
    >> § 53.106. Affidavit of
    Completion
    >>
    >>
    >> (a) An owner may file with the
    county clerk of the county in which
    >> the property is located an
    affidavit of completion. The
    affidavit
    >> must contain:
    >>
    >> (1) the name and address of the
    owner;
    >>
    >> (2) the name and address of the
    original contractor;
    >>
    >> (3) a description, legally
    sufficient for identification, of
    the
    >> real property on which the
    improvements are located;
    >>
    >> (4) a description of the
    improvements furnished under the
    original
    >> contract;
    >>
    >> (5) a statement that the
    improvements under the original
    contract
    >> have been completed and the date
    of completion; and
    >>
    >> (6) a conspicuous statement that
    a claimant may not have a lien on
    >> retained funds unless the
    claimant files the affidavit
    claiming a
    >> lien not later than the 30th day
    after the date of completion.
    >>
    >> (b) A copy of the affidavit must
    be sent by certified or registered
    >> mail to the original contractor
    not later than the date the
    >> affidavit is filed and to each
    claimant who sends a notice of lien
    >> liability to the owner under
    Section 53.056, 53.057, 53.058,
    53.252,
    >> or 53.253 not later than the
    date the affidavit is filed or the
    10th
    >> day after the date the owner
    receives the notice of lien
    liability,
    >> whichever is later.
    >>
    >> (c) A copy of the affidavit must
    also be sent to each person who
    >> furnishes labor or materials for
    the property and who furnishes the
    >> owner with a written request for
    the copy. The owner must furnish
    >> the copy to the person not later
    than the date the affidavit is
    >> filed or the 10th day after the
    date the request is received,
    >> whichever is later.
    >>
    >> (d) Except as provided by this
    subsection, an affidavit filed
    under
    >> this section on or before the
    10th day after the date of
    completion
    >> of the improvements is prima
    facie evidence of the date the work
    >> under the original contract is
    completed for purposes of this
    >> subchapter. If the affidavit is
    filed after the 10th day after the
    >> date of completion, the date of
    completion for purposes of this
    >> subchapter is the date the
    affidavit is filed. This subsection
    does
    >> not apply to a person to whom
    the affidavit was not sent as
    required
    >> by this section.
    >>
    >> (e) Repealed by Acts 1999, 76th
    Leg., ch. 889, § 12, eff. Sept. 1,
    >> 1999.
    >> [Sections 53.107 to 53.120
    reserved for expansion]
    >>
    >> SUBCHAPTER F PRIORITIES AND
    PREFERENCES
    >>
    >> § 53.121. Preference Over Other
    Creditors
    >>
    >>
    >> All subcontractors, laborers,
    and materialmen who have a
    mechanic's
    >> lien have preference over other
    creditors of the original
    >> contractor.
    >> § 53.122. Equality of Mechanic's
    Liens
    >>
    >>
    >> (a) Except as provided by
    Subchapter E [FN1] and Section
    53.124(e),
    >> perfected mechanic's liens are
    on equal footing without reference
    to
    >> the date of filing the affidavit
    claiming the lien.
    >>
    >> (b) If the proceeds of a
    foreclosure sale of property are
    >> insufficient to discharge all
    mechanic's liens against the
    property,
    >> the proceeds shall be paid pro
    rata on the perfected mechanic's
    >> liens on which suit is brought.
    >>
    >> (c) This chapter does not affect
    the contract between the owner and
    >> the original contractor as to
    the amount, manner, or time of
    payment
    >> of the contract price.
    >> § 53.123. Priority of Mechanic's
    Lien Over Other Liens
    >>
    >>
    >> (a) Except as provided by this
    section, a mechanic's lien attaches
    >> to the house, building,
    improvements, or railroad property
    in
    >> preference to any prior lien,
    encumbrance, or mortgage on the
    land
    >> on which it is located, and the
    person enforcing the lien may have
    >> the house, building,
    improvement, or any piece of the
    railroad
    >> property sold separately.
    >>
    >> (b) The mechanic's lien does not
    affect any lien, encumbrance, or
    >> mortgage on the land or
    improvement at the time of the
    inception of
    >> the mechanic's lien, and the
    holder of the lien, encumbrance, or
    >> mortgage need not be made a
    party to a suit to foreclose the
    >> mechanic's lien.
    >> § 53.124. Inception of
    Mechanic's Lien
    >>
    >>
    >> (a) Except as provided by
    Subsection (e), for purposes of
    Section
    >> 53.123, the time of inception of
    a mechanic's lien is the
    >> commencement of construction of
    improvements or delivery of
    >> materials to the land on which
    the improvements are to be located
    >> and on which the materials are
    to be used.
    >>
    >> (b) The construction or
    materials under Subsection (a) must
    be
    >> visible from inspection of the
    land on which the improvements are
    >> being made.
    >>
    >> (c) An owner and original
    contractor may jointly file an
    affidavit
    >> of commencement with the county
    clerk of the county in which the
    >> land is located not later than
    the 30th day after the date of
    actual
    >> commencement of construction of
    the improvements or delivery of
    >> materials to the land. The
    affidavit must contain:
    >>
    >> (1) the name and address of the
    owner;
    >>
    >> (2) the name and address of each
    original contractor, known at the
    >> time to the owner, that is
    furnishing labor, service, or
    materials
    >> for the construction of the
    improvements;
    >>
    >> (3) a description, legally
    sufficient for identification, of
    the
    >> property being improved;
    >>
    >> (4) the date the work actually
    commenced; and
    >>
    >> (5) a general description of the
    improvement.
    >>
    >> (d) An affidavit filed in
    compliance with this section is
    prima
    >> facie evidence of the date of
    the commencement of the improvement
    >> described in the affidavit. The
    time of inception of a mechanic's
    >> lien arising from work described
    in an affidavit of commencement is
    >> the date of commencement of the
    work stated in the affidavit.
    >>
    >> (e) The time of inception of a
    lien that is created under Section
    >> 53.021(c) or (d) is the date of
    recording of an affidavit of lien
    >> under Section 53.052. The
    priority of a lien claimed by a
    person
    >> entitled to a lien under Section
    53.021(c) or (d) with respect to
    >> other mechanic's liens is
    determined by the date of
    recording. A
    >> lien created under Section 53.021
    (c) or (d) is not valid or
    >> enforceable against a grantee or
    purchaser who acquires an interest
    >> in the real property before the
    time of inception of the lien.
    >> [Sections 53.125 to 53.150
    reserved for expansion]
    >>
    >> SUBCHAPTER G RELEASE AND
    FORECLOSURE; ACTION ON CLAIM TEXAS
    PROPERTY
    >>
    >> § 53.151. Enforcement of
    Remedies Against Money Due Original
    >> Contractor or Subcontractor
    >>
    >>
    >> (a) A creditor of an original
    contractor may not collect, enforce
    a
    >> security interest against,
    garnish, or levy execution on the
    money
    >> due the original contractor or
    the contractor's surety from the
    >> owner, and a creditor of a
    subcontractor may not collect,
    enforce a
    >> security interest against,
    garnish, or levy execution on the
    money
    >> due the subcontractor, to the
    prejudice of the subcontractors,
    >> mechanics, laborers,
    materialmen, or their sureties.
    >>
    >> (b) A surety issuing a payment
    bond or performance bond in
    >> connection with the improvements
    has a priority claim over other
    >> creditors of its principal to
    contract funds to the extent of any
    >> loss it suffers or incurs. That
    priority does not excuse the surety
    >> from paying any obligations that
    it may have under its payment
    >> bonds.
    >> § 53.152. Release of Claim or
    Lien
    >>
    >>
    >> (a) When a debt for labor or
    materials is satisfied or paid by
    >> collected funds, the person who
    furnished the labor or materials
    >> shall, not later than the 10th
    day after the date of receipt of a
    >> written request, furnish to the
    requesting person a release of the
    >> indebtedness and any lien
    claimed, to the extent of the
    indebtedness
    >> paid. An owner, the original
    contractor, or any person making
    the
    >> payment may request the release.
    >>
    >> (b) A release of lien must be in
    a form that would permit it to be
    >> filed of record.
    >> § 53.153. Defense of Actions
    >>
    >>
    >> (a) If an affidavit claiming a
    mechanic's lien is filed by a
    person
    >> other than the original
    contractor, the original contractor
    shall
    >> defend at his own expense a suit
    brought on the claim.
    >>
    >> (b) If the suit results in
    judgment on the lien against the
    owner or
    >> the owner's property, the owner
    is entitled to deduct the amount of
    >> the judgment and costs from any
    amount due the original contractor.
    >> If the owner has settled with
    the original contractor in full,
    the
    >> owner is entitled to recover
    from the original contractor any
    amount
    >> paid for which the original
    contractor was originally liable.
    >> § 53.154. Foreclosure
    >>
    >>
    >> A mechanic's lien may be
    foreclosed only on judgment of a
    court of
    >> competent jurisdiction
    foreclosing the lien and ordering
    the sale of
    >> the property subject to the
    lien.
    >> § 53.155. Transfer of Property
    Sold
    >>
    >>
    >> If the house, building,
    improvement, or any piece of
    railroad
    >> property is sold separately, the
    officer making the sale shall place
    >> the purchaser in possession. The
    purchaser is entitled to a
    >> reasonable time after the date
    of purchase within which to remove
    >> the purchased property.
    >> § 53.156. Costs and Attorney's
    Fees
    >>
    >>
    >> In any proceeding to foreclose a
    lien or to enforce a claim against
    >> a bond issued under Subchapter
    H, I, or J [FN1] or in any
    proceeding
    >> to declare that any lien or
    claim is invalid or unenforceable
    in
    >> whole or in part, the court may
    award costs and reasonable
    >> attorney's fees as are equitable
    and just.
    >> § 53.157. Discharge of Lien
    >>
    >>
    >> A mechanic's lien or affidavit
    claiming a mechanic's lien filed
    >> under Section 53.052 may be
    discharged of record by:
    >>
    >> (1) recording a lien release
    signed by the claimant under
    Section
    >> 53.152;
    >>
    >> (2) failing to institute suit to
    foreclose the lien in the county in
    >> which the property is located
    within the period prescribed by
    >> Section 53.158, 53.175, or
    53.208;
    >>
    >> (3) recording the original or
    certified copy of a final judgment
    or
    >> decree of a court of competent
    jurisdiction providing for the
    >> discharge;
    >>
    >> (4) filing the bond and notice
    in compliance with Subchapter H;
    >> [FN1]
    >>
    >> (5) filing the bond in
    compliance with Subchapter I; [FN2]
    or
    >>
    >> § 53.158. Period for Bringing
    Suit to Foreclose Lien
    >>
    >> (a) Except as provided by
    Subsection (b), suit must be
    brought to
    >> foreclose the lien within two
    years after the last day a claimant
    >> may file the lien affidavit
    under Section 53.052 or within one
    year
    >> after completion, termination,
    or abandonment of the work under
    the
    >> original contract under which
    the lien is claimed, whichever is
    >> later.
    >>
    >> (b) For a claim arising from a
    residential construction project,
    >> suit must be brought to
    foreclose the lien within one year
    after the
    >> last day a claimant may file a
    lien affidavit under Section 53.052
    >> or within one year after
    completion, termination, or
    abandonment of
    >> the work under the original
    contract under which the lien is
    >> claimed, whichever is later.
    >>
    >>
    >> On 3/15/05, v wrote:
    >>> Have you checked the revised
    >>> codes? Joisey is two years.
    Used to
    >>> be 20. With the option to renew
    the
    >>> lien in the twenyfirst year.
    Then
    >>> it ran till paid.
    >>>
    >>>
    >>> On 3/15/05, roosta wrote:
    >>>> On 3/15/05, Curmudgeon wrote:
    >>>>> Perhaps someone can pitch in
    if
    >>> there is some peculiarity in
    >>>>> Texas law. The general rule
    is
    >>> that mechanics liens expire
    >>>>> after one year if they are
    not
    >>> foreclosed. In other words,
    >>>>> you can't just sit on it. You
    >>> either foreclose or lose the
    >>>>> lien.
    >>>>
    >>>
    http://www.capitol.state.tx.us/statu
    >>> tes/pr.toc.htm
    >>>> PROPERTY CODE
    >>>> Title 5
    >>>> CHAPTER 53. MECHANIC'S,
    >>> CONTRACTOR'S, OR MATERIALMAN'S
    LIEN

    Posts on this thread, including this one
  • machenics lein / texas, 3/15/05, by debi zerby.
  • Re: machenics lein / texas, 3/15/05, by roosta.
  • Re: machenics lein / texas, 3/15/05, by Curmudgeon.
  • Re: machenics lein / texas, 3/15/05, by roosta.
  • Re: machenics lein / texas Roo, 3/15/05, by v.
  • Re: machenics lein / texas Roo, 3/15/05, by Curmudgeon.
  • Re: machenics lein / texas Roo, 3/15/05, by Curmudgeon---Don't Open My Last Post.
  • Re: machenics lein / Time out for Mudge, 3/15/05, by v.
  • Re: machenics lein last post, 3/15/05, by roosta.
  • Re: machenics lein last post Roo, 3/15/05, by v.
  • Re: machenics lein last post Roo, 3/16/05, by Michael.
  • Re: machenics lein last post Mikey, 3/16/05, by roosta.
  • Re: machenics lein last post Roo, 3/16/05, by Michael.
  • Re: machenics lein last post Roo, 3/16/05, by v.
  • Re: machenics lein last post V, 3/17/05, by Michael.


  Site Map:  Home Chatboards Legal Jobs Classified Ads Search Contacts Advertise
  © 1996 - 2013. All Rights Reserved. Please review our Terms of Use, Mission Statement, and Privacy Policy.